United States › Grid › Interconnection queues › New Jersey
OFFSHORE WIND · PJMOffshore wind project AI1-110, Monmouth County
Offshore wind project AI1-110, Monmouth County is a 1,310 MW offshore wind request in interconnection study in the PJM interconnection queue, in Monmouth County, New Jersey, connecting to JCPL.
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI1-110
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- JCPL
- Connection point (POI)
- Larrabee 230 kV V
- Location
- Monmouth County, New Jersey
- Technology
- Offshore Wind: 1,310 MW
- Total requested
- 1,310 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 1 September 2022
- Proposed online date
- December 2029
Location
Marker shows the centre of Monmouth County; the queue data does not give exact sites.
Power plants in New Jersey · Transmission lines in New Jersey
Other requests in Monmouth County
- Monmouth Solar 1Solar · 15.4 MW · agreement signed
- Offshore wind project AI1-001, Monmouth CountyOffshore wind · 2,100 MW · in study
- Offshore wind project AJ1-015, Monmouth CountyOffshore wind · 1,342 MW · in study
- Battery storage project AI2-068, Monmouth CountyBattery storage · 250 MW · in study
- Battery storage project AI2-069, Monmouth CountyBattery storage · 250 MW · in study
- Port Belford Solar FarmSolar · 19.3 MW · in study
- Atlantic-RedBank 34.5kV SolarSolar · 20.0 MW · built
- Plumsted Energy Storage FacilityBattery storage · 20.0 MW · built
- Tinton Falls SolarSolar · 16.9 MW · built
- Northpark Solar Farm #2Solar · 9.0 MW · built
- Northpark Solar Farm #1Solar · 8.0 MW · built
- Lakewood-Farmingdale Road Storage FacilityBattery storage · 7.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem