United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in PJM (Mid-Atlantic, Midwest) (2011 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown28922.9 GW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn28922.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

289 requests Β· page 1 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project X2-082, Chesterfield County
Gas
1,575 MWWithdrawn / abandoned Chesterfield, VAPJM Jul 2011target 2015
Onshore wind project X1-020, Cass County
Onshore wind
1,500 MWWithdrawn / abandoned Cass, INPJM Feb 2011target 2018
Gas project X1-013, Lebanon County
Gas
1,018 MWWithdrawn / abandoned Lebanon, PAPJM Feb 2011target 2015
Gas project X3-102, Charles County
Gas
971 MWWithdrawn / abandoned Charles, MDPJM Oct 2011target 2016
Gas project X3-103, Charles County
Gas
971 MWWithdrawn / abandoned Charles, MDPJM Oct 2011target 2016
Mattawoman Energy
Gas
894 MWWithdrawn / abandoned Prince George's, MDPJM Oct 2011target 2022
Gas project X2-030, Charles County
Gas
830 MWWithdrawn / abandoned Charles, MDPJM May 2011target 2016
Gas project X4-020, York County
Gas
800 MWWithdrawn / abandoned York, PAPJM Nov 2011target 2017
Gas project X4-026, Prince George's County
Gas
792 MWWithdrawn / abandoned Prince George's, MDPJM Nov 2011target 2015
Gas project X3-089, Middlesex County
Gas
744 MWWithdrawn / abandoned Middlesex, NJPJM Oct 2011target 2016
Gas project W4-044, Charles County
Gas
725 MWWithdrawn / abandoned Charles, MDPJM Jan 2011target 2015
Offshore wind project X1-017, Atlantic County
Offshore wind
720 MWWithdrawn / abandoned Atlantic, NJPJM Feb 2011target 2016
Gas project X2-050, Essex County
Gas
705 MWWithdrawn / abandoned Essex, NJPJM Jun 2011target 2016
Gas project X3-068, York County
Gas
678 MWWithdrawn / abandoned York, PAPJM Oct 2011target 2017
Gas project X3-051
Gas
610 MWWithdrawn / abandoned OHPJM Sep 2011target 2017
Gas project X3-076, Fauquier County
Gas
510 MWWithdrawn / abandoned Fauquier, VAPJM Oct 2011target 2015
Emerson Creek Wind Farm
Onshore wind
500 MWWithdrawn / abandoned Huron, OHPJM Mar 2011target 2018
Gas project X3-088, Montgomery County
Gas
440 MWWithdrawn / abandoned Montgomery, MDPJM Oct 2011target 2016
Onshore wind project X1-040, Dekalb County
Onshore wind
360 MWWithdrawn / abandoned Dekalb, INPJM Mar 2011target 2013
Offshore wind project X2-037, Atlantic County
Offshore wind
350 MWWithdrawn / abandoned Atlantic, NJPJM Jun 2011
Gas project X4-021, York County
Gas
320 MWWithdrawn / abandoned York, PAPJM Nov 2011target 2017
Gas project X2-066, Sussex County
Gas
312 MWWithdrawn / abandoned Sussex, DEPJM Jul 2011target 2016
Gas project X2-067, Kent County
Gas
309 MWWithdrawn / abandoned Kent, DEPJM Jul 2011target 2016
Gas project X3-014, Sussex County
Gas
300 MWWithdrawn / abandoned Sussex, DEPJM Aug 2011target 2016
Edge Moor Units EM6, EM7; Hay Road Units 5,6,7,8
Gas
291 MWWithdrawn / abandoned New Castle, DEPJM Apr 2011target 2018
Gas project X1-064A_AT13, Summit County
Gas
268 MWWithdrawn / abandoned Summit, OHPJM Apr 2011target 2014
Onshore wind project X1-041, Marshall County
Onshore wind
262 MWWithdrawn / abandoned Marshall, INPJM Mar 2011target 2013
Onshore wind project X3-030, Marion County
Onshore wind
245 MWWithdrawn / abandoned Marion, OHPJM Aug 2011target 2015
Gas project X2-019, Lake County
Gas
225 MWWithdrawn / abandoned Lake, ILPJM May 2011target 2015
Coal project X1-027, Scioto County
Coal
200 MWWithdrawn / abandoned Scioto, OHPJM Mar 2011target 2014
Onshore wind project X2-020, Erie County
Onshore wind
200 MWWithdrawn / abandoned Erie, PAPJM May 2011target 2014
Onshore wind project X2-021, Erie County
Onshore wind
154 MWWithdrawn / abandoned Erie, PAPJM May 2011target 2013
Great Bay Wind Farm
Onshore wind
150 MWWithdrawn / abandoned Somerset, MDPJM Apr 2011target 2018
Onshore wind project X3-031, Allen County
Onshore wind
150 MWWithdrawn / abandoned Allen, OHPJM Aug 2011target 2015
Onshore wind project X3-036, Grant County
Onshore wind
150 MWWithdrawn / abandoned Grant, WVPJM Aug 2011target 2012
Gas project X3-006, Berks County
Gas
150 MWWithdrawn / abandoned Berks, PAPJM Aug 2011target 2014
Onshore wind project X2-058, Hancock County
Onshore wind
150 MWWithdrawn / abandoned Hancock, OHPJM Jun 2011target 2012
Gas project X1-080, Prince George County
Gas
135 MWWithdrawn / abandoned Prince George, VAPJM Apr 2011target 2015
Gas project X4-018, Hudson County
Gas
110 MWWithdrawn / abandoned Hudson, NJPJM Nov 2011target 2015
Onshore wind project X2-039, Ashland County
Onshore wind
100 MWWithdrawn / abandoned Ashland, OHPJM Jun 2011target 2013
Solar project X3-022, Adams County
Solar
100 MWWithdrawn / abandoned Adams, PAPJM Aug 2011target 2014
Other project X3-039, Crawford County
Other
96.0 MWWithdrawn / abandoned Crawford, PAPJM Aug 2011target 2014
Coal project X4-025, Greenup County
Coal
80.0 MWWithdrawn / abandoned Greenup, KYPJM Nov 2011target 2018
Coal project X2-086, Grant County
Coal
77.0 MWWithdrawn / abandoned Grant, WVPJM Jul 2011target 2014
Onshore wind project X1-018, Mifflin County
Onshore wind
75.0 MWWithdrawn / abandoned Mifflin, PAPJM Feb 2011target 2013
Onshore wind project X1-019, Dauphin County
Onshore wind
60.0 MWWithdrawn / abandoned Dauphin, PAPJM Feb 2011target 2013
Gas project X4-007, Charles County
Gas
60.0 MWWithdrawn / abandoned Charles, MDPJM Nov 2011target 2015
6011 Greenwich Windpark, LLC
Onshore wind
60.0 MWWithdrawn / abandoned Huron, OHPJM Aug 2011target 2017
Gas project X4-003, Washington County
Gas
56.0 MWWithdrawn / abandoned Washington, OHPJM Nov 2011target 2015
Onshore wind project X2-023, Sullivan County
Onshore wind
51.0 MWWithdrawn / abandoned Sullivan, PAPJM May 2011target 2013
Page 1 of 6

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)