United States › Grid › Interconnection queues › Delaware
GAS · PJMEdge Moor Units EM6, EM7; Hay Road Units 5,6,7,8
Edge Moor Units EM6, EM7; Hay Road Units 5,6,7,8 is a 291 MW gas request withdrawn in the PJM interconnection queue, in New Castle County, Delaware, connecting to DPL.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2011 (completed)
- Withdrawn / abandonedNov 2017 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- X1-074
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- DPL
- Connection point (POI)
- Hay Road 230kV
- Location
- New Castle County, Delaware
- Technology
- Gas: 291 MW
- Total requested
- 291 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Withdrawn
- Entered queue
- 27 April 2011
- Proposed online date
- June 2018
- Withdrawn
- November 2017
Location
Marker shows the centre of New Castle County; the queue data does not give exact sites.
Other requests in New Castle County
- Battery storage project AH2-051, New Castle CountyBattery storage · 200 MW · in study
- Solar project AG2-447, New Castle CountySolar · 20.0 MW · in study
- Other project AI2-025, New Castle CountyOther · 10.0 MW · in study
- Cedar Creek SolarSolar · 19.8 MW · suspended
- Cedar Creek SolarSolar · 19.8 MW · suspended
- Cedar Creek SolarSolar · 18.8 MW · suspended
- Cedar Creek SolarSolar · 15.9 MW · suspended
- Hay Road 5, 6, 7Gas · 545 MW · built
- Garrison Energy CenterGas · 309 MW · built
- Delaware CityOther · 250 MW · built
- Delaware City/Motiva Unit G6Gas · 60.0 MW · built
- New Castle SolarSolar · 50.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem