ONSHORE WIND Β· PJM

Onshore wind project X1-018, Mifflin County

Onshore wind project X1-018, Mifflin County is a 75.0 MW onshore wind request withdrawn in the PJM interconnection queue, in Mifflin County, Pennsylvania, connecting to PENELEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2011 (completed)
  2. Withdrawn / abandonedJan 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
X1-018
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
Lewistown 230kV
Location
Mifflin County, Pennsylvania
Technology
Wind: 75.0 MW
Total requested
75.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study
Queue status
Withdrawn
Entered queue
28 February 2011
Proposed online date
August 2013
Withdrawn
January 2012

Location

Marker shows the centre of Mifflin County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Mifflin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem