Completed queue projects in PJM (Mid-Atlantic, Midwest) (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown723,127 MW
Active in queue4,774 MW44 requests
Agreement signed3,742 MW30 requests
Withdrawn23618.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

72 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Hardin Energy Center β€šΓ„Γ¬ Phase 2
Solar
150 MWOperating Hardin, OHPJM Oct 20172024
Bitter Ridge Wind Farm
Onshore wind
130 MWOperating Jay, INPJM Mar 20172020
Hilltop Energy Center Facility
Gas
130 MWOperating Greene, PAPJM Mar 20172021
Yellowbud Solar
Solar
127 MWOperating Ross, OHPJM Feb 20172022
Yellowbud Solar
Solar
127 MWOperating Ross, OHPJM Nov 20172022
Dodson Creek Solar
Solar
117 MWOperating Ross, OHPJM Feb 20172025
Ross County Solar
Solar
100 MWOperating Ross, OHPJM Feb 20172025
Riverstart Solar Park III
Solar
100 MWOperating Randolph, INPJM Mar 20172024
Lower Mount Bethel
Gas
86.6 MWOperating Northampton, PAPJM Jul 20172019
Adams Solar LLC
Solar
80.0 MWOperating Adams, PAPJM Jun 20172024
Piney Creek Solar
Solar
80.0 MWOperating Halifax, VAPJM Oct 20172023
Foxglove Solar
Solar
75.0 MWOperating Frederick, VAPJM Oct 20172024
CPV Maryland
Gas
75.0 MWOperating Charles, MDPJM Sep 20172019
Hillcrest Solar Facility
Solar
75.0 MWOperating Brown, OHPJM Feb 20172020
Wythe County Solar Project
Solar
75.0 MWOperating Wythe, VAPJM Mar 20172025
Bedford Solar Center
Solar
70.0 MWOperating City Of Chesapeake, VAPJM Jul 20172021
Nestlewood Solar
Solar
70.0 MWOperating Clermont, OHPJM Mar 20172023
Great Cover Solar LLC
Solar
70.0 MWOperating Fulton, PAPJM Nov 20172024
Waverly Solar
Solar
68.0 MWOperating Sussex, VAPJM Sep 20172024
Phillips Island CT1, CT2, CT3, and ST4
Gas
67.0 MWOperating Delaware, PAPJM Sep 20172020
Freedom Generation Plant
Gas
65.0 MWOperating Luzerne, PAPJM Mar 20172023
Foxhound Solar
Solar
64.2 MWOperating Halifax, VAPJM Sep 20172024
Troy Energy
Gas
60.0 MWOperating Wood, OHPJM Sep 20172022
American Beech Solar
Solar
60.0 MWOperating Halifax, NCPJM Mar 20172025
Rock Springs Units #3 & #4
Gas
60.0 MWOperating Cecil, MDPJM Jan 20172017
Carvers Creek Solar
Solar
50.0 MWOperating Gloucester, VAPJM Aug 20172024
Powells Creek Solar
Solar
50.0 MWOperating Halifax, VAPJM Mar 20172023
Clinton Solar
Solar
49.9 MWOperating Clinton, OHPJM Dec 20172025
Blue Harvest Solar Park
Solar
49.9 MWOperating Putnam, OHPJM Sep 20172023
Timber Road Solar Park
Solar
49.9 MWOperating Paulding, OHPJM Sep 20172024
University Park North Energy Center
Gas
46.0 MWOperating Will, ILPJM Mar 20172023
Alton Post Office Solar
Solar
45.9 MWOperating Halifax, VAPJM Aug 20172025
Rockford I Energy Center
Gas
40.0 MWOperating Winnebago, ILPJM Mar 20172021
DC Cook Generating Plant Unit No. 2
Nuclear
38.0 MWOperating Berrien, MIPJM Mar 20172017
Freemont Energy Center
Gas
38.0 MWOperating Sandusky, OHPJM Aug 20172021
Ripley Solar
Solar
27.5 MWOperating Charles, MDPJM Mar 20172023
Warren County Power Station
Gas
20.0 MWOperating Warren, VAPJM Mar 20172018
Solar project AD1-061, Franklin County
Solar
20.0 MWOperating Franklin, PAPJM Aug 20172022
Halifax County Solar
Solar
20.0 MWOperating Halifax, VAPJM Aug 20172024
Bluebird Solar
Solar
20.0 MWOperating Harrison, KYPJM Feb 20172025
Carroll County Energy LLC
Gas
20.0 MWOperating Carroll, OHPJM Jan 20172020
Ross County Solar
Solar
20.0 MWOperating Ross, OHPJM Sep 20172025
Maplewood Solar
Solar
20.0 MWOperating Pittsylvania, VAPJM May 20172022
Big Plain 2
Solar
20.0 MWOperating Madison, OHPJM Sep 20172023
Yellowbud Solar
Solar
20.0 MWOperating Ross, OHPJM Aug 20172022
Powells Creek Solar
Solar
20.0 MWOperating Halifax, VAPJM Sep 20172023
Gloucester Solar
Solar
19.8 MWOperating Gloucester, VAPJM Dec 20172019
Ladysmith Combustion Turbines Unit 1
Gas
19.0 MWOperating Caroline, VAPJM Mar 20172019
Ladysmith Combustion Turbines Unit 2
Gas
19.0 MWOperating Caroline, VAPJM Mar 20172019
Briel Farm Solar
Solar
18.8 MWOperating Henrico, VAPJM Mar 20172020
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)