United States › Grid › Interconnection queues › Virginia
SOLAR · PJMWythe County Solar Project
Wythe County Solar Project is a 75.0 MW solar request built and operating in the PJM interconnection queue, in Wythe County, Virginia, connecting to AEP.
Request details
- Queue ID
- AC2-123
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Jacksons Ferry 138kV
- Location
- Wythe County, Virginia
- Technology
- Solar: 75.0 MW
- Total requested
- 75.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 25 March 2017
- Agreement signed
- 29 March 2021
- Proposed online date
- March 2025
- Came online
- April 2025
Location
Marker shows the centre of Wythe County; the queue data does not give exact sites.
Other requests in Wythe County
- Wythe County Solar ProjectBattery storage · 52.2 MW · agreement signed
- Solar project AH2-069, Wythe CountySolar · 250 MW · in study
- Solar + storage project AH2-382, Wythe CountySolar + storage · 75.0 MW · in study
- Solar + storage project AG2-462, Wythe CountySolar + storage · 150 MW · withdrawn
- Solar project AE2-196, Wythe CountySolar · 94.6 MW · withdrawn
- Solar project AC1-155, Wythe CountySolar · 50.0 MW · withdrawn
- Solar project AG2-432, Wythe CountySolar · 45.0 MW · withdrawn
- Silverside SolarSolar · 18.2 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem