SOLAR + STORAGE Β· PJM

Solar + storage project AG2-462, Wythe County

Solar + storage project AG2-462, Wythe County is a 150 MW solar + storage request withdrawn in the PJM interconnection queue, in Wythe County, Virginia, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandonedJun 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-462
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Developer
May Solar LLC
Connection point (POI)
Progress Park - Glen Lyn 138 kV
Location
Wythe County, Virginia
Technology
Solar: 150 MW Β· Battery
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Entered queue
30 March 2021
Proposed online date
October 2024
Withdrawn
June 2025

Location

Marker shows the centre of Wythe County; the queue data does not give exact sites.

Power plants in Virginia Β· Transmission lines in Virginia