United States βΊ Grid βΊ Interconnection queues βΊ Virginia
SOLAR Β· PJMSolar project AE2-196, Wythe County
Solar project AE2-196, Wythe County is a 94.6 MW solar request withdrawn in the PJM interconnection queue, in Wythe County, Virginia, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2019 (completed)
- Withdrawn / abandonedMar 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AE2-196
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Mt. Airy-Wythe 138 kV
- Location
- Wythe County, Virginia
- Technology
- Solar: 94.6 MW
- Total requested
- 94.6 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 19 March 2019
- Proposed online date
- December 2022
- Withdrawn
- March 2020
Location
Marker shows the centre of Wythe County; the queue data does not give exact sites.
Other requests in Wythe County
- Wythe County Solar ProjectBattery storage Β· 52.2 MW Β· agreement signed
- Solar project AH2-069, Wythe CountySolar Β· 250 MW Β· in study
- Solar + storage project AH2-382, Wythe CountySolar + storage Β· 75.0 MW Β· in study
- Wythe County Solar ProjectSolar Β· 75.0 MW Β· built
- Solar + storage project AG2-462, Wythe CountySolar + storage Β· 150 MW Β· withdrawn
- Solar project AC1-155, Wythe CountySolar Β· 50.0 MW Β· withdrawn
- Solar project AG2-432, Wythe CountySolar Β· 45.0 MW Β· withdrawn
- Silverside SolarSolar Β· 18.2 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem