Freemont Energy Center

Freemont Energy Center is a 38.0 MW gas request built and operating in the PJM interconnection queue, in Sandusky County, Ohio, connecting to ATSI.

Queue statusOperating
  1. PlanningQueued Aug 2017 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingFeb 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AD1-052
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Connection point (POI)
Freemont Energy Center
Location
Sandusky County, Ohio
Technology
Gas: 38.0 MW
Total requested
38.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
10 August 2017
Proposed online date
October 2020
Came online
February 2021

Location

Marker shows the centre of Sandusky County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Sandusky County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem