United States › Grid › Interconnection queues › Ohio

SOLAR · PJM

Blue Harvest Solar Park

Blue Harvest Solar Park is a 49.9 MW solar request built and operating in the PJM interconnection queue, in Putnam County, Ohio, connecting to AEP.

Queue statusOperating
  1. PlanningQueued Sep 2017 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingNov 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AD1-101
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Continental 69 kV
Location
Putnam County, Ohio
Technology
Solar: 49.9 MW
Total requested
49.9 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
21 September 2017
Proposed online date
June 2023
Came online
November 2023

Location

Marker shows the centre of Putnam County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Putnam County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem