United States › Grid › Interconnection queues › Ohio
SOLAR · PJMHillcrest Solar Facility
Hillcrest Solar Facility is a 75.0 MW solar request built and operating in the PJM interconnection queue, in Brown County, Ohio, connecting to DEOK.
Request details
- Queue ID
- AC2-066
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- DEOK
- Connection point (POI)
- Hillcrest 138kV
- Location
- Brown County, Ohio
- Technology
- Solar: 75.0 MW
- Total requested
- 75.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 24 February 2017
- Proposed online date
- December 2020
- Came online
- December 2020
Location
Marker shows the centre of Brown County; the queue data does not give exact sites.
Other requests in Brown County
- Hillcrest Solar FacilitySolar · 125 MW · built
- Stuart Electric Generating StationCoal · 20.5 MW · built
- Bio Energy Landfill FacilityOther · 4.8 MW · built
- Solar project AH1-273, Brown CountySolar · 160 MW · withdrawn
- Battery storage project AG2-359, Brown CountyBattery storage · 125 MW · withdrawn
- Solar project AC1-022, Brown CountySolar · 60.0 MW · withdrawn
- Solar project AC2-062, Brown CountySolar · 55.0 MW · withdrawn
- Solar project AH1-113, Brown CountySolar · 20.0 MW · withdrawn
- Solar project AA1-126, Brown CountySolar · 20.0 MW · withdrawn
- Solar project AA1-125, Brown CountySolar · 20.0 MW · withdrawn
- Solar project AH1-114, Brown CountySolar · 20.0 MW · withdrawn
- Solar project W3-098, Brown CountySolar · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem