United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in PJM (Mid-Atlantic, Midwest) (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1089,751 MW
Active in queue2,290 MW31 requests
Agreement signed1,820 MW21 requests
Withdrawn25023.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

108 requests Β· page 1 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Jackson Generation
Gas
1,201 MWOperating Will, ILPJM Oct 20162022
Guernsey Power Station
Gas
1,100 MWOperating Guernsey, OHPJM Mar 20162023
Guernsey Power Station
Gas
550 MWOperating Guernsey, OHPJM Aug 20162022
Spotsylvania Energy Center
Solar
485 MWOperating Spotsylvania, VAPJM Oct 20162020
Hannibal Port Power Project
Gas
485 MWOperating Monroe, OHPJM Apr 20162021
Highland County Solar
Solar
400 MWOperating Highland, OHPJM Oct 20162024
Blooming Grove WF
Onshore wind
250 MWOperating Mclean, ILPJM Feb 20162020
Cavalier
Solar
240 MWOperating Isle Of Wight, VAPJM Nov 20162024
Top Hat Wind Energy Center
Onshore wind
200 MWOperating Logan, ILPJM Sep 20162025
Alta Farms II
Onshore wind
197 MWOperating Dewitt, ILPJM Mar 20162023
Big Plain
Solar
176 MWOperating Madison, OHPJM Oct 20162023
Willowbrook Solar
Solar
150 MWOperating Highland, OHPJM Oct 20162024
Fort Powhatan Solar
Solar
150 MWOperating Prince George, VAPJM Apr 20162022
Colonial Trail West Solar
Solar
142 MWOperating Surry, VAPJM Apr 20162019
Hardin Energy Center
Solar
130 MWOperating Hardin, OHPJM Apr 20162020
Shillelagh Solar
Solar
118 MWOperating City Of Chesapeake, VAPJM Dec 20162023
Smithton Generation Station
Gas
110 MWOperating Westmoreland, PAPJM Jul 20162018
Midland Wind Farm
Onshore wind
101 MWOperating Henry, ILPJM Aug 20162024
Moccasin Creek Solar
Solar
100 MWOperating Edgecombe, NCPJM Mar 20162020
Maplewood Solar
Solar
100 MWOperating Pittsylvania, VAPJM Sep 20162022
Riverstart Solar Park
Solar
100 MWOperating Randolph, INPJM Oct 20162021
CPV Fairview Energy Center
Gas
100 MWOperating Cambria, PAPJM Oct 20162019
Riverstart Solar Park
Solar
100 MWOperating Randolph, INPJM Oct 20162021
Sadler Solar
Solar
100 MWOperating Greensville, VAPJM Apr 20162021
Dresden
Gas
98.0 MWOperating Muskingum, OHPJM Oct 20162017
Spring Grove I Solar
Solar
97.9 MWOperating Surry, VAPJM Oct 20162020
Indeck Niles Energy Center
Gas
91.0 MWOperating Cass, MIPJM Oct 20162021
Belcher Solar
Solar
88.2 MWOperating Louisa, VAPJM Apr 20162021
Greensville County Solar Project
Solar
80.0 MWOperating Greensville, VAPJM Apr 20162020
Bluebird Solar
Solar
80.0 MWOperating Harrison, KYPJM Sep 20162025
Chase City Solar
Solar
80.0 MWOperating Mecklenburg, VAPJM Mar 20162020
Brink Solar Project
Solar
80.0 MWOperating Greensville, VAPJM Mar 20162024
Lone Tree Wind
Onshore wind
79.4 MWOperating Bureau, ILPJM Oct 20162020
Timber Road IV Wind Farm (Southern Phase)
Onshore wind
75.9 MWOperating Paulding, OHPJM Oct 20162020
Wilkinson Solar Energy Center
Solar
74.0 MWOperating Hyde, NCPJM Apr 20162019
Hawtree Creek
Solar
65.0 MWOperating Warren, NCPJM Aug 20162021
Joliet Units 7 and 8
Gas
64.0 MWOperating Will, ILPJM Oct 20162020
Jones Farm Lane Solar
Solar
64.0 MWOperating Queen Anne's, MDPJM Apr 20162025
Pine Glade Solar
Solar
62.5 MWOperating Orange, VAPJM Oct 20162024
Stagecoach Solar
Solar
60.0 MWOperating Halifax, VAPJM Sep 20162021
American Beech Solar
Solar
60.0 MWOperating Alamance, NCPJM Oct 20162025
Altavista Solar
Solar
60.0 MWOperating Campbell, VAPJM Oct 20162020
Sunnybrook Farm Solar
Solar
51.0 MWOperating Halifax, VAPJM Oct 20162022
New Castle Solar
Solar
50.0 MWOperating New Castle, DEPJM Apr 20162022
Lawrenceburg Generating Plant
Gas
50.0 MWOperating Dearborn, INPJM Oct 20162019
Waverly Solar
Solar
50.0 MWOperating Sussex, VAPJM May 20162024
Whitethorn Solar
Solar
50.0 MWOperating Pittsylvania, VAPJM Oct 20162021
Richfield Solar and Storage
Solar
50.0 MWOperating Dorchester, MDPJM Apr 20162024
Lawrenceburg Generating Plant
Gas
50.0 MWOperating Dearborn, INPJM Oct 20162019
Buckeye Plains Solar
Solar
49.9 MWOperating Pickaway, OHPJM Nov 20162025
Page 1 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)