Wilkinson Solar Energy Center

Wilkinson Solar Energy Center is a 74.0 MW solar request built and operating in the PJM interconnection queue, in Hyde County, North Carolina, connecting to Dominion.

Queue statusOperating
  1. PlanningQueued Apr 2016 (completed)
  2. ConsentedMar 2020 (completed)
  3. Construction (completed)
  4. OperatingNov 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AB2-169
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Pantago-Five Points 115kV
Location
Hyde County, North Carolina
Technology
Solar: 74.0 MW
Total requested
74.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
29 April 2016
Agreement signed
4 March 2020
Proposed online date
June 2021
Came online
November 2019

Location

Marker shows the centre of Hyde County; the queue data does not give exact sites.

Power plants in North Carolina · Transmission lines in North Carolina

Other requests in Hyde County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem