Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown29463.3 GW
Active in queue15.6 GW89 requests
Agreement signed0.0 MW0 requests
Withdrawn29463.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

294 requests · page 1 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
EI Steinway 1.1
Onshore wind · Beacon Wind
1,600 MWWithdrawn / abandoned Queens, NYNYISO Sep 2024
Atlantic Shores Offshore Wind Project 5
Offshore wind · ATLANTIC SHORES OFFSHORE WIND BIGHT LLC
1,400 MWWithdrawn / abandoned Suffolk, NYNYISO Aug 2024
Atlantic Shores Offshore Wind Project 3
Offshore wind · ATLANTIC SHORES OFFSHORE WIND LLC
1,400 MWWithdrawn / abandoned Kings, NYNYISO Aug 2024
Atlantic Shores Offshore Wind Project 4
Offshore wind · Atlantic Shores Offshore Wind Bight LLC
1,400 MWWithdrawn / abandoned Kings, NYNYISO Aug 2024
New Scotland BESS
Battery storage · Eden DevCo
1,350 MWWithdrawn / abandoned Albany, NYNYISO Feb 2024
New Scotland BESS
Battery storage · New Scotland BESS
1,350 MWWithdrawn / abandoned Albany, NYNYISO Aug 2024
Cosw Bceh
Offshore wind · Community Offshore Wind, LLC
1,310 MWWithdrawn / abandoned Kings, NYNYISO Aug 2024
Bluepoint Wind 2
Offshore wind · Bluepoint Wind LLC
1,310 MWWithdrawn / abandoned Nassau, NYNYISO Aug 2024
Long Island Wind
Offshore wind · Bay State Wind
1,310 MWWithdrawn / abandoned Suffolk, NYNYISO Sep 2024
COSW Barrett
Offshore wind · Community Offshore Wind, LLC
1,310 MWWithdrawn / abandoned Suffolk, NYNYISO Aug 2024
Queensboro Renewable Express Circuit A
Onshore wind · Queensboro Development, LLC
1,310 MWWithdrawn / abandoned Queens, NYNYISO Aug 2024
EI Steinway 1
Offshore wind · Beacon Wind LLC
1,300 MWWithdrawn / abandoned Queens, NYNYISO Sep 2024
EI Melville
Offshore wind · Empire Wind 2 LLC
1,240 MWWithdrawn / abandoned NYNYISO Aug 2024
Agr NY1
Offshore wind · Avangrid Renewables, LLC
1,229 MWWithdrawn / abandoned Nassau, NYNYISO Oct 2024
Liberty BESS
Battery storage · North Bergen Liberty Generating LLC
1,200 MWWithdrawn / abandoned Hudson, NJNYISO Sep 2024
Vineyard Mid-Atlantic East
Offshore wind · Vineyard Mid-Atlantic LLC
1,187 MWWithdrawn / abandoned Nassau, NYNYISO Aug 2024
Robinson Hill BESS
Battery storage · Oakdale BESS
1,117 MWWithdrawn / abandoned Broome, NYNYISO Aug 2024
Oakdale BESS
Battery storage · Eden Devco LP
1,091 MWWithdrawn / abandoned Broome, NYNYISO Feb 2024
Dover NY BESS
Battery storage · DOVER PLAINS ENERGY PROPERTIES LLC
1,000 MWWithdrawn / abandoned Dutchess, NYNYISO Oct 2024
Bethlehem Energy Center Uprate
Gas · GB II New York
926 MWWithdrawn / abandoned Albany, NYNYISO Oct 2024
Vineyard Northeast
Onshore wind · Vineyard Northeast LLC
884 MWWithdrawn / abandoned Nassau, NYNYISO Aug 2024
Bayonne Energy Storage I
Battery storage · AMBAR POWER HOLDCO LLC
600 MWWithdrawn / abandoned Hudson, NJNYISO Oct 2024
Declaration Energy Center
Solar + storage · Declaration Energy Center, LLC
550 MWWithdrawn / abandoned Seneca, NYNYISO Sep 2024
Chinook Energy Storage Center
Battery storage · Hydrostor USA Holdings, Inc , a subsidiary of Hydrostor Inc
500 MWWithdrawn / abandoned Lewis, NYNYISO Sep 2024
Braen Energy Storage Phase 1
Battery storage · Braen Energy LLC
500 MWWithdrawn / abandoned Rockland, NYNYISO Aug 2024
Antelope Energy Storage Center
Battery storage · Antelope Energy Storage LLC
500 MWWithdrawn / abandoned Lewis, NYNYISO Sep 2024
Marcy BESS 3
Battery storage · The Commodore Storage, LLC
435 MWWithdrawn / abandoned Oneida, NYNYISO Sep 2024
Black Cherry BESS
Battery storage · Black Cherry Wind Power, LLC
400 MWWithdrawn / abandoned Mckean, PANYISO Oct 2024
Green Isles Energy Storage
Battery storage · CEDAR HOLDCO LLC
400 MWWithdrawn / abandoned Suffolk, NYNYISO Oct 2024
Bayonne Energy Storage II
Battery storage · AMBAR POWER HOLDCO LLC
400 MWWithdrawn / abandoned Hudson, NJNYISO Oct 2024
PA-Hockenberry LLC
Solar · PA-Hockenberry LLC
400 MWWithdrawn / abandoned Jefferson, PANYISO Sep 2024
Arthur Kill Upgrade
Gas · Arthur Kill Power
370 MWWithdrawn / abandoned Richmond, NYNYISO Oct 2024
5Mile Storage Project
Battery storage · Five Mile Energy, LLC
360 MWWithdrawn / abandoned Cattaraugus, NYNYISO Oct 2024
Snowy Knoll Wind Project
Wind + storage · Snowy Knoll Wind Project, LLC
350 MWWithdrawn / abandoned Oneida, NYNYISO Sep 2024
Wheelhouse Solar Energy Center
Solar + storage · Wheelhouse Solar Energy Center, LLC
350 MWWithdrawn / abandoned Herkimer, NYNYISO Sep 2024
West Laurens
Solar · ACE DevCo NC, LLC
350 MWWithdrawn / abandoned Otsego, NYNYISO Sep 2024
Black Cherry Wind 1
Onshore wind · Black Cherry Wind Power, LLC
350 MWWithdrawn / abandoned Cameron, PANYISO Sep 2024
Ez Energy Solutions LLC 5802 BESS
Battery storage · EZ ENERGY SOLUTIONS LLC
329 MWWithdrawn / abandoned Kings, NYNYISO Oct 2024
Athens Energy Storage
Battery storage · Athens Energy Storage LLC
300 MWWithdrawn / abandoned Greene, NYNYISO Oct 2024
Knickerbocker Energy Storage
Battery storage · Knickerbocker Energy Storage Project, LLC
300 MWWithdrawn / abandoned Rensselaer, NYNYISO Sep 2024
Huntley Energy Storage
Battery storage · CEDAR HOLDCO LLC
300 MWWithdrawn / abandoned Erie, NYNYISO Oct 2024
Sugar Loaf Energy Storage II
Battery storage · Hambletonian Energy Storage II LLC
300 MWWithdrawn / abandoned Orange, NYNYISO Oct 2024
Field Day Solar
Solar + storage · Field Day Solar Project, LLC
300 MWWithdrawn / abandoned Oneida, NYNYISO Sep 2024
Genovia Storage
Battery storage · Genovia Storage LLC
300 MWWithdrawn / abandoned Genesee, NYNYISO Sep 2024
Genovia Storage
Battery storage · Genovia Storage LLC
300 MWWithdrawn / abandoned Genesee, NYNYISO Sep 2024
PA-Fritz Kiln LLC
Solar · PA-Fritz Kiln LLC
300 MWWithdrawn / abandoned Elk, PANYISO Oct 2024
Coopers Corner BESS
Battery storage · ACE DevCo NC,LLC
300 MWWithdrawn / abandoned Sullivan, NYNYISO Aug 2024
Genovia Storage
Battery storage · Genovia Storage LLC
300 MWWithdrawn / abandoned Genesee, NYNYISO Sep 2024
Cedar Lake Storage
Battery storage · Emeren US, LLC
300 MWWithdrawn / abandoned St. Lawrence, NYNYISO Sep 2024
Oyster shore Energy storage
Battery storage · Shore Rd ESS LLC
275 MWWithdrawn / abandoned Nassau, NYNYISO Aug 2024
Page 1 of 6

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)