United States βΊ Grid βΊ Interconnection queues βΊ New York
OFFSHORE WIND Β· NYISOAgr NY1
Agr NY1 is a 1,229 MW offshore wind request withdrawn in the NYISO interconnection queue, in Nassau County, New York, connecting to NYPA.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2024 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- C24-343
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYPA
- Developer
- Avangrid Renewables, LLC
- Connection point (POI)
- East Garden City 345 kV
- Location
- Nassau County, New York
- Technology
- Offshore Wind: 1,229 MW
- Total requested
- 1,229 MW
- Queue status
- Withdrawn
- Entered queue
- 11 October 2024
Location
Marker shows the centre of Nassau County; the queue data does not give exact sites.
Other requests in Nassau County
- Vineyard Mid-Atlantic WestOffshore wind Β· 1,321 MW Β· in study
- Glenwood Gas PlantGas Β· 79.9 MW Β· built
- Glenwood Gas PlantGas Β· 79.9 MW Β· built
- BrentwoodGas Β· 44.0 MW Β· built
- BrentwoodGas Β· 44.0 MW Β· built
- OW Ocean Winds East 3Offshore wind Β· 1,600 MW Β· withdrawn
- EI Empire ESS IIWind + storage Β· 1,440 MW Β· withdrawn
- Vineyard Wind IOffshore wind Β· 1,403 MW Β· withdrawn
- Bluepoint Wind 4Offshore wind Β· 1,382 MW Β· withdrawn
- Vineyard Mid-Atlantic 3Offshore wind Β· 1,330 MW Β· withdrawn
- Vineyard Mid-Atlantic 2Offshore wind Β· 1,330 MW Β· withdrawn
- NY Wind - New Bridge RoadOffshore wind Β· 1,325 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem