OFFSHORE WIND · NYISO

Vineyard Mid-Atlantic 2

Vineyard Mid-Atlantic 2 is a 1,330 MW offshore wind request withdrawn in the NYISO interconnection queue, in Nassau County, New York, connecting to NYPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1443
Grid region
NYISO (New York)
Utility / transmission owner
NYPA
Developer
Vineyard Mid-Atlantic
Connection point (POI)
East Garden City 345 kV Substation
Location
Nassau County, New York
Technology
Offshore Wind: 1,330 MW
Total requested
1,330 MW
Queue status
Withdrawn
Entered queue
28 September 2022

Location

Marker shows the centre of Nassau County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Nassau County