United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in MISO (Midcontinent) (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown233,679 MW
Active in queue3,679 MW23 requests
Agreement signed325 MW1 requests
Withdrawn101,143 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

23 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Replacing 749 MW of coal generation with BESS; Campbell 3
Other
749 MWIn study Ottawa, MIMISO Nov 2023target 2028
Solar project J1598, Calcasieu Parish County
Solar
325 MWAgreement signed Calcasieu Parish, LAMISO Dec 2023target 2026
Onshore wind project MPC04500, Grand Forks County
Onshore wind
258 MWIn study Grand Forks, NDMISO Sep 2023target 2028
Replacing 220 MW of coal generation with BESS; Trenton Channel 9
Other
220 MWIn study Wayne, MIMISO Oct 2023target 2025
Battery storage project J1895, Kenosha County
Battery storage
200 MWIn study Kenosha, WIMISO Oct 2023target 2024
Solar project J1684, Starke County
Solar
200 MWIn study Starke, INMISO Aug 2023target 2029
Solar project J2759, Arkansas County
Solar
170 MWIn study Arkansas, ARMISO Sep 2023target 2029
Solar project J2955, Saline County
Solar
150 MWIn study Saline, ARMISO Nov 2023target 2026
Solar project J1914, Presque Isle County
Solar
150 MWIn study Presque Isle, MIMISO Oct 2023target 2026
Surplus; J33/J734
Other
135 MWIn study Ford, ILMISO May 2023target 2026
Solar project J2801, Woodruff County
Solar
130 MWIn study Woodruff, ARMISO Sep 2023target 2026
Solar project J1939, Saginaw County
Solar
125 MWIn study Saginaw, MIMISO Oct 2023target 2023
Solar + storage project J2152, Tangipahoa Parish County
Solar + storage
120 MWIn study Tangipahoa Parish, LAMISO Nov 2023target 2025
Surplus; J442
Other
120 MWIn study Codington, SDMISO Oct 2023target 2026
Surplus; G736
Other
120 MWIn study Codington, SDMISO Oct 2023target 2026
Solar project J1916, Branch County
Solar
100 MWIn study Branch, MIMISO Oct 2023target 2026
replacing 100MW of un-built solar with BESS; Mayhew
Other
100 MWIn study Benton, MNMISO Nov 2023target 2025
Battery storage project J2555, Ingham County
Battery storage
100 MWIn study Ingham, MIMISO Aug 2023target 2026
Surplus; J1369
Other
50.0 MWIn study Dubois, INMISO Apr 2023target 2024
Surplus; J1386
Other
50.0 MWIn study Lake, INMISO Apr 2023target 2024
Replacing 49 MW of gas generation with BESS; Sterlington
Other
49.0 MWIn study Ouachita, LAMISO Oct 2023target 2025
Surplus; J1102
Other
40.0 MWIn study Logan, ILMISO Oct 2023target 2025
Other project J2116, Cook County
Other
18.0 MWIn study Cook, MNMISO Dec 2023target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)