United States › Grid › Interconnection queues › Arkansas
SOLAR · MISOSolar project J2801, Woodruff County
Solar project J2801, Woodruff County is a 130 MW solar request in interconnection study in the MISO interconnection queue, in Woodruff County, Arkansas, connecting to ENTERGY ARKANSAS.
Queue statusIn planning
- PlanningQueued Sep 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2801
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY ARKANSAS
- Connection point (POI)
- AECC HUNTER NORTH - MCCRORY 161.0kV
- Location
- Woodruff County, Arkansas
- Technology
- Solar: 130 MW
- Total requested
- 130 MW
- Service type
- Energy only (ERIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 11 September 2023
- Proposed online date
- September 2026
Location
Marker shows the centre of Woodruff County; the queue data does not give exact sites.
Other requests in Woodruff County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem