United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in MISO (Midcontinent) (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown26738.5 GW
Active in queue23.7 GW136 requests
Agreement signed1,055 MW8 requests
Withdrawn26738.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

267 requests Β· page 1 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J1848, Van Buren County
Gas
1,235 MWWithdrawn / abandoned Van Buren, MIMISO Aug 2021target 2023
Solar project J2168, Jefferson County
Solar
693 MWWithdrawn / abandoned Jefferson, TXMISO Aug 2021target 2024
Solar project J2176, Calcasieu Parish County
Solar
680 MWWithdrawn / abandoned Calcasieu Parish, LAMISO Aug 2021target 2025
Replace 15 MW of ALTW.FPL_DAEC Unit with Battery; Duane Arnold
Other
640 MWWithdrawn / abandoned Linn, IAMISO Sep 2021target 2023
Onshore wind project J1893, Morton County
Onshore wind
500 MWWithdrawn / abandoned Morton, NDMISO Nov 2021target 2024
Solar project J2086, Barnes County
Solar
500 MWWithdrawn / abandoned Barnes, NDMISO Aug 2021target 2025
Onshore wind project MPC04300, Steele County
Onshore wind
457 MWWithdrawn / abandoned Steele, NDMISO Jul 2021target 2024
Wind + storage project J2039, Sangamon County
Wind + storage
400 MWWithdrawn / abandoned Sangamon, ILMISO Aug 2021target 2024
Solar project J2174, Tunica County
Solar
390 MWWithdrawn / abandoned Tunica, MSMISO Aug 2021target 2025
Replace 350 MW of ALTW.FPL_DAEC Unit with Solar; Duane Arnold
Other
350 MWWithdrawn / abandoned Otter Tail, MNMISO Feb 2021target 2023
Solar project J2194, Sullivan County
Solar
350 MWWithdrawn / abandoned Sullivan, INMISO Aug 2021target 2024
Solar project J2175, Washington County
Solar
350 MWWithdrawn / abandoned Washington, MSMISO Aug 2021target 2025
Onshore wind project J2241, Benton County
Onshore wind
320 MWWithdrawn / abandoned Benton, INMISO Aug 2021target 2024
Solar project J1886, Henderson County
Solar
300 MWWithdrawn / abandoned Henderson, KYMISO Aug 2021target 2025
Solar project J2310, Beauregard Parish County
Solar
300 MWWithdrawn / abandoned Beauregard Parish, LAMISO Sep 2021target 2024
Solar project J2225, Henderson County
Solar
300 MWWithdrawn / abandoned Henderson, KYMISO Aug 2021target 2025
Solar project J1885, Henderson County
Solar
300 MWWithdrawn / abandoned Henderson, KYMISO Aug 2021target 2025
Solar project J2246, Henderson County
Solar
300 MWWithdrawn / abandoned Henderson, KYMISO Aug 2021target 2025
Onshore wind project J2038, Montgomery County
Onshore wind
300 MWWithdrawn / abandoned Montgomery, INMISO Aug 2021target 2024
Solar project J2234, Henderson County
Solar
300 MWWithdrawn / abandoned Henderson, KYMISO Aug 2021target 2025
Solar project J2207, Henderson County
Solar
300 MWWithdrawn / abandoned Henderson, KYMISO Aug 2021target 2025
Solar + storage project J2020, Beauregard Parish County
Solar + storage
260 MWWithdrawn / abandoned Beauregard Parish, LAMISO Aug 2021target 2024
Solar project J1868, Winn Parish County
Solar
260 MWWithdrawn / abandoned Winn Parish, LAMISO Aug 2021target 2024
Onshore wind project J1865, Hardin County
Onshore wind
250 MWWithdrawn / abandoned Hardin, IAMISO Aug 2021target 2024
Solar project J2028, Crittenden County
Solar
250 MWWithdrawn / abandoned Crittenden, ARMISO Aug 2021target 2024
Solar project J2164, Pike County
Solar
250 MWWithdrawn / abandoned Pike, INMISO Aug 2021target 2024
Onshore wind project J1864, Cerro Gordo County
Onshore wind
250 MWWithdrawn / abandoned Cerro Gordo, IAMISO Aug 2021target 2024
Surplus; J1419
Other
250 MWWithdrawn / abandoned MISO Aug 2021target 2022
Onshore wind project J1989, Brown County
Onshore wind
250 MWWithdrawn / abandoned Brown, SDMISO Aug 2021target 2025
Onshore wind project J1990, Stutsman County
Onshore wind
250 MWWithdrawn / abandoned Stutsman, NDMISO Nov 2021target 2025
Solar project J1857, Cross County
Solar
250 MWWithdrawn / abandoned Cross, ARMISO Nov 2021target 2026
Solar + storage project J2076, San Jacinto County
Solar + storage
225 MWWithdrawn / abandoned San Jacinto, TXMISO Aug 2021target 2024
Battery storage project J2095, Tama County
Battery storage
212 MWWithdrawn / abandoned Tama, IAMISO Aug 2021target 2024
Solar project J1737, Rush County
Solar
210 MWWithdrawn / abandoned Rush, INMISO Oct 2021target 2023
Battery storage project J2204, St. Clair County
Battery storage
200 MWWithdrawn / abandoned St. Clair, ILMISO Oct 2021target 2024
Solar project J1911, Livingston County
Solar
200 MWWithdrawn / abandoned Livingston, MIMISO Aug 2021target 2023
Solar + storage project J2041, Jefferson County
Solar + storage
200 MWWithdrawn / abandoned Jefferson, TXMISO Aug 2021target 2025
Solar project J1912, Sanilac County
Solar
200 MWWithdrawn / abandoned Sanilac, MIMISO Aug 2021target 2023
Solar project J2251, Grant County
Solar
200 MWWithdrawn / abandoned Grant, INMISO Aug 2021target 2024
Solar project J2065, Pipestone County
Solar
200 MWWithdrawn / abandoned Pipestone, MNMISO Jul 2021target 2024
Solar project J1913, Midland County
Solar
200 MWWithdrawn / abandoned Midland, MIMISO Aug 2021target 2023
Solar project J2183, Pointe Coupee Parish County
Solar
200 MWWithdrawn / abandoned Pointe Coupee Parish, LAMISO Sep 2021target 2022
Solar project J2259, Hendricks County
Solar
200 MWWithdrawn / abandoned Hendricks, INMISO Aug 2021target 2024
Battery storage project J1884, Columbia County
Battery storage
200 MWWithdrawn / abandoned Columbia, WIMISO Aug 2021target 2024
Solar project J2037, Olmsted County
Solar
200 MWWithdrawn / abandoned Olmsted, MNMISO Jul 2021target 2024
Battery storage project J2105, Franklin County
Battery storage
200 MWWithdrawn / abandoned Franklin, IAMISO Aug 2021target 2024
Solar + storage project J2201, Harrison County
Solar + storage
200 MWWithdrawn / abandoned Harrison, INMISO Dec 2021target 2024
Solar project J2295, Sullivan County
Solar
200 MWWithdrawn / abandoned Sullivan, INMISO Sep 2021target 2025
Solar project J2113, Daviess County
Solar
200 MWWithdrawn / abandoned Daviess, KYMISO Aug 2021target 2024
Solar + storage project J2056, Lenawee County
Solar + storage
200 MWWithdrawn / abandoned Lenawee, MIMISO Aug 2021target 2025
Page 1 of 6

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)