Solar project J2295, Sullivan County

Solar project J2295, Sullivan County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Sullivan County, Indiana, connecting to HOOSIER ENERGY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedApr 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2295
Grid region
MISO (Midcontinent)
Utility / transmission owner
HOOSIER ENERGY
Connection point (POI)
Merom Substation 345kV
Location
Sullivan County, Indiana
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: DPP 2
Queue status
Withdrawn
Entered queue
9 September 2021
Proposed online date
April 2025
Withdrawn
April 2023

Location

Marker shows the centre of Sullivan County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Sullivan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem