SOLAR Β· MISO

Solar project J2259, Hendricks County

Solar project J2259, Hendricks County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Hendricks County, Indiana, connecting to WABASH VALLEY POWER ASSOCIATION, INC..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedOct 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2259
Grid region
MISO (Midcontinent)
Utility / transmission owner
WABASH VALLEY POWER ASSOCIATION, INC.
Connection point (POI)
Amo 345kV
Location
Hendricks County, Indiana
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 August 2021
Proposed online date
November 2024
Withdrawn
October 2024

Location

Marker shows the centre of Hendricks County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Hendricks County