BATTERY STORAGE Β· MISO

Battery storage project J3339, Hendricks County

Battery storage project J3339, Hendricks County is a 100 MW battery storage request withdrawn in the MISO interconnection queue, in Hendricks County, Indiana, connecting to DUKE ENERGY INDIANA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3339
Grid region
MISO (Midcontinent)
Utility / transmission owner
DUKE ENERGY INDIANA
Connection point (POI)
AMO
Location
Hendricks County, Indiana
Technology
Battery: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
16 April 2024
Proposed online date
September 2028
Withdrawn
December 2025

Location

Marker shows the centre of Hendricks County; the queue data does not give exact sites.