Solar project J1385, Hendricks County

Solar project J1385, Hendricks County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Hendricks County, Indiana, connecting to DUKE ENERGY INDIANA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedAug 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1385
Grid region
MISO (Midcontinent)
Utility / transmission owner
DUKE ENERGY INDIANA
Connection point (POI)
Stilesville 138 kV Substation
Location
Hendricks County, Indiana
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
29 April 2019
Proposed online date
August 2022
Withdrawn
August 2021

Location

Marker shows the centre of Hendricks County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Hendricks County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem