United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in MISO (Midcontinent) (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown7722.8 GW
Active in queue736 MW2 requests
Agreement signed736 MW2 requests
Withdrawn7722.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

77 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Nuclear project J371, Ogle County
Nuclear
2,325 MWWithdrawn / abandoned Ogle, ILMISO Jun 2014target 2016
Nuclear project J372, Rock Island County
Nuclear
1,373 MWWithdrawn / abandoned Rock Island, ILMISO Jun 2014target 2019
Gas project J404, Jefferson Parish County
Gas
1,078 MWWithdrawn / abandoned Jefferson Parish, LAMISO Nov 2014target 2020
Gas project J425, St. Charles Parish County
Gas
999 MWWithdrawn / abandoned St. Charles Parish, LAMISO Nov 2014
Gas project J402, Orleans Parish County
Gas
991 MWWithdrawn / abandoned Orleans Parish, LAMISO Nov 2014target 2019
Gas project J336, Calumet County
Gas
845 MWWithdrawn / abandoned Calumet, WIMISO May 2014
Gas project J338, Winnebago County
Gas
845 MWWithdrawn / abandoned Winnebago, WIMISO May 2014
Gas project J355, Adair County
Gas
810 MWWithdrawn / abandoned Adair, IAMISO May 2014target 2017
Gas project J363, Pottawattamie County
Gas
810 MWWithdrawn / abandoned Pottawattamie, IAMISO May 2014target 2016
Gas project J388, Vermilion County
Gas
800 MWWithdrawn / abandoned Vermilion, ILMISO Sep 2014target 2018
Gas project J353, Dickinson County
Gas
725 MWWithdrawn / abandoned Dickinson, MIMISO May 2014
Gas project J383, Manitowoc County
Gas
571 MWWithdrawn / abandoned Manitowoc, WIMISO Aug 2014target 2019
Gas project J337, Winnebago County
Gas
551 MWWithdrawn / abandoned Winnebago, WIMISO May 2014
Gas project J335, Calumet County
Gas
551 MWWithdrawn / abandoned Calumet, WIMISO May 2014
Gas project J389, Rock County
Gas
550 MWWithdrawn / abandoned Rock, WIMISO Sep 2014
Gas project J364, Adair County
Gas
464 MWWithdrawn / abandoned Adair, IAMISO May 2014target 2016
Gas project J365, Pottawattamie County
Gas
464 MWWithdrawn / abandoned Pottawattamie, IAMISO May 2014target 2018
Gas project J369, Newton County
Gas
393 MWWithdrawn / abandoned Newton, TXMISO May 2014target 2017
Gas project J352, Dickinson County
Gas
362 MWWithdrawn / abandoned Dickinson, MIMISO May 2014
Gas project J331, Calcasieu Parish County
Gas
338 MWWithdrawn / abandoned Calcasieu Parish, LAMISO May 2014
Gas project J394, Marquette County
Gas
327 MWWithdrawn / abandoned Marquette, MIMISO Sep 2014target 2016
Gas project MPC02700, Pennington County
Gas
320 MWWithdrawn / abandoned Pennington, MNMISO Jun 2014target 2020
Onshore wind project J342, Buchanan County
Onshore wind
305 MWWithdrawn / abandoned Buchanan, IAMISO May 2014target 2015
Onshore wind project J410, Fayette County
Onshore wind
300 MWWithdrawn / abandoned Fayette, IAMISO Nov 2014target 2016
Coal project J358, Woodbury County
Coal
280 MWWithdrawn / abandoned Woodbury, IAMISO May 2014target 2016
Gas project J413, Marquette County
Gas
243 MWWithdrawn / abandoned Marquette, MIMISO Nov 2014target 2017
Gas project J359, Woodbury County
Gas
232 MWWithdrawn / abandoned Woodbury, IAMISO May 2014target 2015
Gas project J366, Pottawattamie County
Gas
232 MWWithdrawn / abandoned Pottawattamie, IAMISO May 2014target 2016
Gas project J356, Polk County
Gas
232 MWWithdrawn / abandoned Polk, IAMISO May 2014
Gas project J398, Marquette County
Gas
204 MWWithdrawn / abandoned Marquette, MIMISO Sep 2014
Onshore wind project J346, Nodaway County
Onshore wind
201 MWWithdrawn / abandoned Nodaway, MOMISO May 2014
Onshore wind project J408, Sanilac County
Onshore wind
200 MWWithdrawn / abandoned Sanilac, MIMISO Nov 2014target 2018
Solar project J368, Lee County
Solar
200 MWWithdrawn / abandoned Lee, ARMISO May 2014target 2016
Onshore wind project J415, Franklin County
Onshore wind
200 MWWithdrawn / abandoned Franklin, IAMISO Nov 2014target 2019
Solar project J380, Lee County
Solar
199 MWWithdrawn / abandoned Lee, ARMISO Jul 2014
Gas project J397, Marquette County
Gas
153 MWWithdrawn / abandoned Marquette, MIMISO Sep 2014target 2016
Onshore wind project J321, Sanilac County
Onshore wind
151 MWWithdrawn / abandoned Sanilac, MIMISO Jan 2014target 2015
Onshore wind project J409, Fayette County
Onshore wind
150 MWWithdrawn / abandoned Fayette, IAMISO Nov 2014target 2015
Coal project J357, Woodbury County
Coal
135 MWWithdrawn / abandoned Woodbury, IAMISO May 2014target 2018
Gas project J423, Wayne County
Gas
125 MWWithdrawn / abandoned Wayne, MIMISO Nov 2014
Onshore wind project J375, Ford County
Onshore wind
124 MWWithdrawn / abandoned Ford, ILMISO Jul 2014target 2015
Onshore wind project J414, Freeborn County
Onshore wind
120 MWWithdrawn / abandoned Freeborn, MNMISO Nov 2014target 2019
Gas project J424, Wayne County
Gas
120 MWWithdrawn / abandoned Wayne, MIMISO Nov 2014
Gas project J360, Scott County
Gas
116 MWWithdrawn / abandoned Scott, IAMISO May 2014
Gas project J361, Pottawattamie County
Gas
116 MWWithdrawn / abandoned Pottawattamie, IAMISO May 2014
Gas project J362, Polk County
Gas
116 MWWithdrawn / abandoned Polk, IAMISO May 2014target 2016
Gas project J427, Livingston County
Gas
110 MWWithdrawn / abandoned Livingston, MIMISO Nov 2014
Solar project J387, Independence County
Solar
103 MWWithdrawn / abandoned Independence, ARMISO Sep 2014target 2016
Solar project J386, Lonoke County
Solar
103 MWWithdrawn / abandoned Lonoke, ARMISO Sep 2014
Solar project J349, Sherburne County
Solar
100 MWWithdrawn / abandoned Sherburne, MNMISO May 2014target 2016
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)