United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Indiana, MISO (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4015.2 GW
Active in queue15.2 GW40 requests
Agreement signed0.0 MW0 requests
Withdrawn4633 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

40 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Schahfer CCGTs
Gas Β· NIPSCO
2,740 MWIn study Jasper, INMISO Aug 2025target 2028
Gas project J3999, Vermillion County
Gas
1,540 MWIn study Vermillion, INMISO Apr 2025target 2030
Malden CCGT
Gas Β· NIPSCO
1,090 MWIn study Porter, INMISO Aug 2025target 2028
Gas project J3084, Sullivan County
Gas
642 MWIn study Sullivan, INMISO Aug 2025target 2026
Malden BESS
Battery storage Β· NIPSCO
630 MWIn study Porter, INMISO Aug 2025target 2027
Merom Station
Gas Β· Hallador Power
530 MWIn study Sullivan, INMISO Nov 2025target 2028
Mitchell BESS
Battery storage Β· NIPSCO
527 MWIn study Lake, INMISO Aug 2025target 2028
Solar project J3931, Jasper County
Solar
500 MWIn study Jasper, INMISO Feb 2025target 2030
Gas project J4005, Sullivan County
Gas
500 MWIn study Sullivan, INMISO May 2025target 2028
Gas project J4021, Sullivan County
Gas
470 MWIn study Sullivan, INMISO May 2025target 2028
Merom Storage
Solar + storage Β· Hoosier Energy / Solvenz
405 MWIn study Sullivan, INMISO Dec 2025target 2028
Solar project J3942, Vigo County
Solar
365 MWIn study Vigo, INMISO Feb 2025target 2030
Solar project J3943, Vigo County
Solar
337 MWIn study Vigo, INMISO Feb 2025target 2030
Brickyard Energy Storage
Battery storage Β· Brickyard Energy Storge, LLC
310 MWIn study Boone, INMISO Aug 2025target 2028
Solar + storage project J3114, Greene County
Solar + storage
300 MWIn study Greene, INMISO Nov 2025target 2026
Onshore wind project J3910, Newton County
Onshore wind
300 MWIn study Newton, INMISO Feb 2025target 2030
Onshore wind project J4063, Knox County
Onshore wind
300 MWIn study Knox, INMISO Sep 2025target 2030
Sandcut Storage
Solar + storage Β· Hoosier Energy / Solvenz
280 MWIn study Vigo, INMISO Dec 2025target 2028
Onshore wind project J3846, Newton County
Onshore wind
275 MWIn study Newton, INMISO Jan 2025target 2030
Madison County Combustion Turbine
Gas Β· Indiana Municipal Power Agency (IMPA)
268 MWIn study Anderson, INMISO Aug 2025target 2028
Solar + storage project J3978, Sullivan County
Solar + storage
200 MWIn study Sullivan, INMISO Apr 2025target 2029
Solar + storage project J3980, Sullivan County
Solar + storage
200 MWIn study Sullivan, INMISO Apr 2025target 2029
Solar project J2538, Clark County
Solar
200 MWIn study Clark, INMISO Oct 2025target 2026
Solar + storage project J3981, Sullivan County
Solar + storage
200 MWIn study Sullivan, INMISO Apr 2025target 2029
Battery storage project J3948, Posey County
Battery storage
200 MWIn study Posey, INMISO Mar 2025target 2030
Solar project J2848, Hamilton County
Solar
200 MWIn study Hamilton, INMISO Nov 2025target 2025
Solar + storage project J3979, Sullivan County
Solar + storage
200 MWIn study Sullivan, INMISO Apr 2025target 2029
Surplus; J992
Battery storage
200 MWIn study Cass, INMISO Jun 2025target 2026
Solar project J4039, Montgomery County
Solar
200 MWIn study Montgomery, INMISO Jun 2025target 2030
Solar project J4023, Clay County
Solar
185 MWIn study Clay, INMISO Feb 2025target 2029
Surplus
Battery storage
150 MWIn study Greene, INMISO Jan 2025target 2029
Solar + storage project S1120, Knox County
Solar + storage
150 MWIn study Knox, INMISO Sep 2025target 2027
Battery storage project S1112, Pike County
Battery storage
130 MWIn study Pike, INMISO Aug 2025target 2027
Replacing 100 MW of Solar with storage; J1386
Battery storage
100 MWIn study Lake, INMISO Jul 2025target 2028
Surplus; J1190
Battery storage
100 MWIn study Lagrange, INMISO Jul 2025target 2027
Solar project J3896, Knox County
Solar
70.0 MWIn study Knox, INMISO Feb 2025target 2030
Solar project J4034, Vigo County
Solar
70.0 MWIn study Vigo, INMISO Jun 2025target 2030
Solar project J3925, Knox County
Solar
70.0 MWIn study Knox, INMISO Feb 2025target 2030
Solar project J3897, Knox County
Solar
60.0 MWIn study Knox, INMISO Feb 2025target 2030
Battery storage project S1126, Knox County
Battery storage
50.0 MWIn study Knox, INMISO Oct 2025target 2029

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)