United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in CAISO (California) (2011 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Pathfinder Renewable Wind Energy Onshore wind |
3,000 MW | Withdrawn / abandoned |
| Cowboy Mesa Wind Onshore wind |
1,700 MW | Withdrawn / abandoned |
| Eagle Mountain Pump Storage #3 Hydro |
1,400 MW | Withdrawn / abandoned |
| Suncrest Imperial Segs Solar |
1,080 MW | Withdrawn / abandoned |
| Central Valley I Segs Solar |
1,080 MW | Withdrawn / abandoned |
| Kern Solar Ranch (Fka California Solar Ranch) Solar |
1,000 MW | Withdrawn / abandoned |
| WSP 3 Solar |
800 MW | Withdrawn / abandoned |
| CVH Power II Solar |
700 MW | Withdrawn / abandoned |
| Jasper Segs (Fka Sonoran West II) Solar |
540 MW | Withdrawn / abandoned |
| Hidden Hills Ranch Solar |
540 MW | Withdrawn / abandoned |
| Central Valley II Segs Solar |
540 MW | Withdrawn / abandoned |
| Solar Four Solar |
510 MW | Withdrawn / abandoned |
| Alta 15 Onshore wind |
502 MW | Withdrawn / abandoned |
| Blythe Mesa Solar II Solar |
500 MW | Withdrawn / abandoned |
| Mesa Solar Solar |
500 MW | Withdrawn / abandoned |
| Madison Solar Solar |
500 MW | Withdrawn / abandoned |
| Calaveras Wind Project (100/383MW) Other |
483 MW | Withdrawn / abandoned |
| Black Rock 1,2,3,4, & 5,6 Geothermal |
470 MW | Withdrawn / abandoned |
| El Segundo Energy Center 2 ( Fka El Segundo Energy Center-II) Gas |
435 MW | Withdrawn / abandoned |
| Hickory Solar Farm Solar |
400 MW | Withdrawn / abandoned |
| Wellhead Power Kern 3 Gas |
400 MW | Withdrawn / abandoned |
| Soldier Flat Onshore wind |
400 MW | Withdrawn / abandoned |
| Hydrogen Energy California ( Heca ) Project Other |
340 MW | Withdrawn / abandoned |
| Dunnigan Onshore wind |
301 MW | Withdrawn / abandoned |
| Cordelia Hills Wind Power Plant Onshore wind |
301 MW | Withdrawn / abandoned |
| Desert Quartzite Solar Solar |
300 MW | Withdrawn / abandoned |
| CVH Power I Solar |
300 MW | Withdrawn / abandoned |
| CPV North City Gas |
300 MW | Withdrawn / abandoned |
| Re Oasis Solar |
300 MW | Withdrawn / abandoned |
| Lone Tree Wind Onshore wind |
299 MW | Withdrawn / abandoned |
| Loop Ranch Wind Onshore wind |
299 MW | Withdrawn / abandoned |
| Gran Vista Solar + storage |
279 MW | Withdrawn / abandoned |
| Sandy Valley Phase I Segs (Fka Pahrump Valley Segs) Solar |
270 MW | Withdrawn / abandoned |
| Sonoran West I Segs Solar |
270 MW | Withdrawn / abandoned |
| Westlands Lemoore Solar Solar |
250 MW | Withdrawn / abandoned |
| Arlington Valley Solar Energy II Solar |
250 MW | Withdrawn / abandoned |
| Hyder Solar Energy Project Solar |
250 MW | Withdrawn / abandoned |
| Montezuma Wetlands Onshore wind |
250 MW | Withdrawn / abandoned |
| Fort Mojave Solar Farms 2 Solar |
240 MW | Withdrawn / abandoned |
| SP Blythe 1 Solar |
221 MW | Withdrawn / abandoned |
| Desert Bell Solar Solar |
200 MW | Withdrawn / abandoned |
| Mount Signal Solar Farm III Solar |
200 MW | Withdrawn / abandoned |
| Silurian Valley Wind Onshore wind |
200 MW | Withdrawn / abandoned |
| Daggett Solar Project Solar |
200 MW | Withdrawn / abandoned |
| Mojave View Solar Solar |
200 MW | Withdrawn / abandoned |
| Sun Valley Energy Center-1 Solar |
200 MW | Withdrawn / abandoned |
| Tulare Solar Solar |
150 MW | Withdrawn / abandoned |
| Candlewood Wind Onshore wind |
150 MW | Withdrawn / abandoned |
| Acorn Greenworks Solar |
150 MW | Withdrawn / abandoned |
| Maricopa California Solar Farms II Solar |
150 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- CAISO (California)187 Β· 30.0 GW
- PJM (Mid-Atlantic, Midwest)289 Β· 22.9 GW
- Southeast (non-ISO utilities)32 Β· 14.0 GW
- West (non-ISO utilities)157 Β· 12.8 GW
- MISO (Midcontinent)51 Β· 10.5 GW
- SPP (Southwest Power Pool)43 Β· 8,099 MW
- ERCOT (Texas)26 Β· 4,638 MW
- ISO-NE (New England)14 Β· 1,774 MW
- NYISO (New York)9 Β· 1,394 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)