United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

SP Blythe 1

SP Blythe 1 is a 221 MW solar request withdrawn in the CAISO interconnection queue, in Riverside County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2011 (completed)
  2. Withdrawn / abandonedNov 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
798
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Colorado River Substation 230kV
Location
Riverside County, California
Technology
Solar: 221 MW
Total requested
221 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 March 2011
Proposed online date
September 2018
Withdrawn
November 2016

Location

Marker shows the centre of Riverside County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Riverside County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem