SOLAR Β· CAISO

Re Oasis

Re Oasis is a 300 MW solar request withdrawn in the CAISO interconnection queue, in Riverside County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2011 (completed)
  2. Withdrawn / abandonedJun 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
754
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
220kV Red Bluff Substation
Location
Riverside County, California
Technology
Solar: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 March 2011
Proposed online date
December 2014
Withdrawn
June 2011

Location

Marker shows the centre of Riverside County; the queue data does not give exact sites.