United States › Grid › Interconnection queues › California

ONSHORE WIND · CAISO

Cordelia Hills Wind Power Plant

Cordelia Hills Wind Power Plant is a 301 MW onshore wind request withdrawn in the CAISO interconnection queue, in Napa County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2011 (completed)
  2. Withdrawn / abandonedAug 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
868
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Vaca-Bahia 230kV line
Location
Napa County, California
Technology
Wind: 301 MW
Total requested
301 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 November 2011
Proposed online date
October 2016
Withdrawn
August 2012

Location

Marker shows the centre of Napa County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Napa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem