OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 96

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,226638.1 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,226 requests · page 96 of 105
ProjectCapacityStatusLocationRegionQueuedOnline
Other project W4-087, Cook County
Other
3.1 MWWithdrawn / abandoned Cook, ILPJM Jan 2011target 1998
Solar + storage project AE2-213, Gloucester County
Solar + storage
3.1 MWWithdrawn / abandoned Gloucester, NJPJM Mar 2019target 2020
Solar project AB2-140, Harford County
Solar
3.0 MWWithdrawn / abandoned Harford, MDPJM Apr 2016target 2017
BL-Kettle
Solar + storage
3.0 MWWithdrawn / abandoned Blair, PAPJM Mar 2020target 2022
Solar project AG1-300, Cumberland County
Solar
3.0 MWWithdrawn / abandoned Cumberland, NJPJM Sep 2020target 2021
BR-Swissdale
Solar + storage
3.0 MWWithdrawn / abandoned Blair, PAPJM Mar 2020target 2022
Ryan Township Solar I
Solar
3.0 MWWithdrawn / abandoned Schuylkill, PAPJM Apr 2010target 2014
CL-Route 58 R
Solar + storage
3.0 MWWithdrawn / abandoned Clarion, PAPJM Mar 2020target 2022
LA-Blue Rock
Solar + storage
3.0 MWWithdrawn / abandoned Lancaster, PAPJM Mar 2020target 2023
Solar project W2-081, Schuylkill County
Solar
3.0 MWWithdrawn / abandoned Schuylkill, PAPJM Jul 2010target 2011
Solar project X2-094, Middlesex County
Solar
3.0 MWWithdrawn / abandoned Middlesex, NJPJM Jul 2011target 2013
Solar project AE2-103, Ocean County
Solar
3.0 MWWithdrawn / abandoned Ocean, NJPJM Feb 2019target 2020
Other project W4-069, Lycoming County
Other
3.0 MWWithdrawn / abandoned Lycoming, PAPJM Jan 2011target 2012
Solar project AG2-028, Adams County
Solar
3.0 MWWithdrawn / abandoned Adams, PAPJM Oct 2020target 2021
Solar project AG2-393, Buckingham County
Solar
3.0 MWWithdrawn / abandoned Buckingham, VAPJM Mar 2021target 2022
Battery storage project AG1-149, Somerset County
Battery storage
3.0 MWWithdrawn / abandoned Somerset, MDPJM Sep 2020target 2021
Other project AC2-099, Lake County
Other
3.0 MWWithdrawn / abandoned Lake, OHPJM Mar 2017target 2018
Solar project AG1-299, Atlantic County
Solar
3.0 MWWithdrawn / abandoned Atlantic, NJPJM Sep 2020target 2021
CO-Zaners Rohrsburg
Solar + storage
3.0 MWWithdrawn / abandoned City Of Lynchburg, VAPJM Mar 2021target 2024
Solar project AG2-399, Adams County
Solar
3.0 MWWithdrawn / abandoned Adams, PAPJM Mar 2021target 2023
Solar project W3-092, Salem County
Solar
3.0 MWWithdrawn / abandoned Salem, NJPJM Oct 2010target 2011
Solar project AG2-022, Dauphin County
Solar
3.0 MWWithdrawn / abandoned Dauphin, PAPJM Oct 2020target 2021
LH-Decatur
Solar + storage
3.0 MWWithdrawn / abandoned Lehigh, PAPJM Mar 2020target 2026
LA-Buck
Solar + storage
3.0 MWWithdrawn / abandoned Lancaster, PAPJM Mar 2020target 2023
Solar + storage project AH2-176
Solar + storage
3.0 MWWithdrawn / abandoned PJM Mar 2022target 2024
Lincoln Solar Farm
Solar
3.0 MWWithdrawn / abandoned Adams, PAPJM Jul 2010target 2016
PE-Windy Hill
Solar + storage
3.0 MWWithdrawn / abandoned Perry, PAPJM Mar 2020target 2023
Solar project AH1-022, Cumberland County
Solar
3.0 MWWithdrawn / abandoned Cumberland, PAPJM May 2021target 2022
Solar project AE1-046, Atlantic County
Solar
3.0 MWWithdrawn / abandoned Atlantic, NJPJM Jul 2018target 2019
Solar project AB2-018
Solar
3.0 MWWithdrawn / abandoned NCPJM Jan 2016target 2016
Solar project AE2-141, Burlington County
Solar
3.0 MWWithdrawn / abandoned Burlington, NJPJM Mar 2019target 2021
PA York Hess
Solar
3.0 MWWithdrawn / abandoned York, PAPJM Mar 2020target 2022
Solar project AG2-026, Berks County
Solar
3.0 MWWithdrawn / abandoned Berks, PAPJM Oct 2020target 2021
Heatherwoods Solar Farm
Solar
3.0 MWWithdrawn / abandoned Lancaster, PAPJM Apr 2010target 2017
Solar project AD2-069, Burlington County
Solar
3.0 MWWithdrawn / abandoned Burlington, NJPJM Feb 2018target 2019
Solar project AC2-143, Middlesex County
Solar
3.0 MWWithdrawn / abandoned Middlesex, NJPJM Mar 2017target 2019
PA Adams Ramsburg
Solar
3.0 MWWithdrawn / abandoned Adams, PAPJM Jan 2020target 2025
Solar project AG2-025, Cumberland County
Solar
3.0 MWWithdrawn / abandoned Cumberland, PAPJM Oct 2020target 2021
Solar project Y1-024
Solar
3.0 MWWithdrawn / abandoned OHPJM Feb 2012target 2013
Layton Road Solar Farm
Solar
3.0 MWWithdrawn / abandoned Sussex, NJPJM Jan 2011target 2014
Solar + storage project AH2-180
Solar + storage
3.0 MWWithdrawn / abandoned PJM Mar 2022target 2024
Solar project AG2-027, Adams County
Solar
3.0 MWWithdrawn / abandoned Adams, PAPJM Oct 2020target 2021
Solar project AE2-003, Prince George's County
Solar
3.0 MWWithdrawn / abandoned Prince George's, MDPJM Oct 2018target 2019
PE-Dellville
Solar + storage
3.0 MWWithdrawn / abandoned Perry, PAPJM Mar 2020target 2024
Willow Brook Road Solar I
Solar
3.0 MWWithdrawn / abandoned Monmouth, NJPJM Jan 2019target 2022
Solar + storage project AH2-182, Rockingham County
Solar + storage
3.0 MWWithdrawn / abandoned Rockingham, VAPJM Mar 2022target 2024
Other project Y2-057, Wyandot County
Other
3.0 MWWithdrawn / abandoned Wyandot, OHPJM Aug 2012target 2013
Plainsboro 13kV
Solar
3.0 MWWithdrawn / abandoned Middlesex, NJPJM Aug 2017target 2018
Solar project AG2-075, Fayette County
Solar
3.0 MWWithdrawn / abandoned Fayette, OHPJM Jan 2021target 2022
Solar project AE1-045, Atlantic County
Solar
3.0 MWWithdrawn / abandoned Atlantic, NJPJM Jul 2018target 2019
Page 96 of 105

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)