United States βΊ Grid βΊ Interconnection queues βΊ Ohio
SOLAR Β· PJMSolar project Y1-024
Solar project Y1-024 is a 3.0 MW solar request withdrawn in the PJM interconnection queue, connecting to Duke.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2012 (completed)
- Withdrawn / abandonedOct 2012 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- Y1-024
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Duke
- Connection point (POI)
- Felicity 12.5kV
- Location
- Ohio
- Technology
- Solar: 3.0 MW
- Total requested
- 3.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 28 February 2012
- Proposed online date
- October 2013
- Withdrawn
- October 2012
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem