🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Pennsylvania

SOLAR · PJM

Ryan Township Solar I

Ryan Township Solar I is a 3.0 MW solar request withdrawn in the PJM interconnection queue, in Schuylkill County, Pennsylvania, connecting to PPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2010 (completed)
  2. Withdrawn / abandonedDec 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
W1-115
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PPL
Connection point (POI)
Tamanend
Location
Schuylkill County, Pennsylvania
Technology
Solar: 3.0 MW
Total requested
3.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Withdrawn
Entered queue
30 April 2010
Proposed online date
June 2014
Withdrawn
December 2017

Location

Marker shows the centre of Schuylkill County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Schuylkill County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem