🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Pennsylvania

ONSHORE WIND · PJM

Locust Ridge II WF

Locust Ridge II WF is a 100 MW onshore wind request built and operating in the PJM interconnection queue, in Schuylkill County, Pennsylvania, connecting to PPL.

Queue statusOperating
  1. PlanningQueued Apr 2006 (completed)
  2. ConsentedMay 2008 (completed)
  3. Construction (completed)
  4. OperatingApr 2009 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Q27
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PPL
Connection point (POI)
Frackville-Shennandoah 69kV
Location
Schuylkill County, Pennsylvania
Technology
Wind: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
7 April 2006
Agreement signed
9 May 2008
Proposed online date
April 2009
Came online
April 2009

Location

Marker shows the centre of Schuylkill County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Schuylkill County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem