Requests shown6,8521,550.1 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6,852 requests · page 90 of 138
ProjectCapacityStatusLocationRegionQueuedOnline
Edgewood BESS 1
Battery storage · Tempus Power management LLC
102 MWIn study Van Zandt, TXERCOT Nov 2024target 2028
watermelon 7 energy storage
Battery storage · Tempus power management LLC
102 MWIn study Dallas, TXERCOT Feb 2025target 2029
Blackland Prairie 3 Energy Storage
Battery storage · Tempus power management LLC
102 MWIn study Travis, TXERCOT Mar 2025target 2027
San Bernard Solar II
Solar · San Bernard Solar II, LLC
102 MWPaused / redesign Wharton, TXERCOT Mar 2019target 2022
Two Rivers Solar
Solar + storage
102 MWIn study Camden, GASoutheast Mar 2022target 2027
Pajaro Valley Storage
Battery storage
102 MWIn study San Diego, CACAISO Apr 2021target 2030
Battery storage project GEN-2025-SR7, Muskogee County
Battery storage
102 MWIn study Muskogee, OKSPP May 2025target 2026
Opuntia Solar SLF
Solar + storage · Opuntia Solar, LLC
102 MWIn study Refugio, TXERCOT Aug 2021target 2028
Crocus Solar
Solar + storage · Crocus Solar, LLC
102 MWIn study Stephens, TXERCOT Jan 2025target 2028
Roxton Storage
Solar + storage · Roxton Solar, LLC
102 MWIn study Lamar, TXERCOT Nov 2024target 2028
Half Moon 2 BESS
Battery storage
102 MWPaused / redesign Hidalgo, TXERCOT Mar 2022
Droga
Battery storage
102 MWIn study Merced, CACAISO Apr 2023target 2028
Kurtz Solar SLF
Solar + storage · Kurtz Solar, LLC
102 MWIn study Atascosa, TXERCOT Sep 2024target 2029
Pisgah Ridge Solar 2
Solar + storage · Pisgah Ridge Solar 2, LLC
102 MWIn study Navarro, TXERCOT Jul 2021target 2026
Myers Solar
Solar + storage · BT Myers Solar, LLC
102 MWIn study Bee, TXERCOT Jun 2023target 2028
Kennedy Solar
Solar + storage · Kennedy Bypass Solar LLC
102 MWIn study Navarro, TXERCOT Mar 2022target 2028
Jayhawk Solar
Solar · Renewable Energy Ventures, LLC
102 MWIn study Mitchell, TXERCOT Aug 2019target 2025
Battery storage project GEN-2023-SR27, Mayes County
Battery storage
102 MWIn study Mayes, OKSPP Jul 20232024
Gas project CS25-05, Kootenai County
Gas
102 MWIn study Kootenai, IDWest Apr 2025target 2029
Gas project CS25-04, Kootenai County
Gas
102 MWIn study Kootenai, IDWest Apr 2025target 2027
Triangle Ranch Delta
Onshore wind
102 MWPaused / redesign Cottle, TXERCOT Sep 2022target 2025
Rose Quartz BESS
Battery storage · Rose Quartz BESS, LLC
101 MWIn study Dimmit, TXERCOT Sep 2022target 2026
Pisgah Ridge Storage 3
Solar + storage · Pisgah Ridge 3, LLC
101 MWIn study Navarro, TXERCOT Jul 2021target 2026
Blanket Ranch South Solar
Solar + storage · Blanket Ranch South Solar, LLC
101 MWIn study Brown, TXERCOT Jun 2022target 2028
Margay Energy Storage
Battery storage · PowerPulse LLC
101 MWIn study Brazoria, TXERCOT Feb 2025target 2029
Maddox Solar
Solar · Industrial Lima Project LLC
101 MWIn study Grayson, TXERCOT May 2024target 2028
Pinnacle Point Energy Storage
Battery storage · GCI Pinnacle Point, LLC
101 MWIn study Harris, TXERCOT Nov 2023target 2027
Blue Creek Energy Storage
Battery storage · Blue Creek Energy Storage, LLC
101 MWIn study Wharton, TXERCOT Oct 2023target 2028
Kinney County Energy
Battery storage · Kinney County Energy, LLC
101 MWIn study Kinney, TXERCOT Mar 2023target 2027
Lyford Energy
Battery storage · Lyford Energy, LLC
101 MWIn study Willacy, TXERCOT Mar 2023target 2027
Southside Energy
Battery storage · Southside Energy, LLC
101 MWIn study Brazoria, TXERCOT Feb 2023target 2028
Hadrian Energy Storage
Battery storage · Hadrian Energy Storage, LLC
101 MWIn study Wharton, TXERCOT May 2023target 2028
Hynes Bay Energy Storage
Battery storage · Hynes Bay Energy Storage, LLC
101 MWIn study Wharton, TXERCOT Oct 2023target 2027
Strawberry Dunes Solar SLF
Solar + storage · Strawberry Dunes LLC
101 MWIn study Atascosa, TXERCOT Feb 2025target 2028
Solar project G0368, Wasco County
Solar
101 MWIn study Wasco, ORWest Jun 2009target 2027
Saltillo Storage
Battery storage
101 MWPaused / redesign Bastrop, TXERCOT May 2022target 2025
Las Moras Battery
Battery storage · Las Moras Storage, LLC
101 MWIn study Kinney, TXERCOT Jun 2021target 2029
Solar Star Frontier BESS
Battery storage · Solar Star Frontier BESS, LLC
101 MWIn study Cameron, TXERCOT Jun 2023target 2029
Luthor Solar
Solar · TREX US Luthor LLC
101 MWIn study Howard, TXERCOT Jun 2022target 2027
Vaca Storage
Battery storage · Long Mount Storage, LLC
101 MWIn study Calhoun, TXERCOT Mar 2021target 2029
Glory Bee Storage
Solar + storage · Riley Solar LLC
101 MWIn study Erath, TXERCOT Jun 2022target 2026
Sandford Storage
Solar + storage · BT Sandford Solar, LLC
101 MWIn study Wise, TXERCOT Jan 2024target 2028
Long Point Solar II
Solar
101 MWPaused / redesign Brazoria, TXERCOT Jan 2023target 2025
Eiger Energy Storage
Battery storage
101 MWIn study Kern, CACAISO Apr 2021target 2032
Pinewood BESS
Battery storage
101 MWPaused / redesign Brazoria, TXERCOT Sep 2022
Hide Town Energy Storage
Battery storage · Hide Town Energy Storage LLC
101 MWIn study Scurry, TXERCOT Jan 2023target 2028
Inertia BESS 2
Battery storage
101 MWPaused / redesign Haskell, TXERCOT Oct 2020
High Bridge Wind
Onshore wind · High Bridge Wind, LLC
101 MWIn study Chenango, NYNYISO Apr 2018target 2026
Venus Mill Storage
Battery storage
101 MWPaused / redesign Ellis, TXERCOT Mar 2022target 2026
Padrino BESS
Battery storage
101 MWPaused / redesign Hill, TXERCOT Sep 2022
Page 90 of 138

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)