Requests shown4,787563.7 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4,787 requests · page 89 of 96
ProjectCapacityStatusLocationRegionQueuedOnline
Paunch Solar
Solar
2.0 MWOperating Hunterdon, NJPJM Apr 20102013
Charlston LF
Other
2.0 MWOperating Kanawha, WVPJM Apr 20092010
Kumquat Solar
Solar
2.0 MWOperating Wicomico, MDPJM Mar 20202022
Other project 203, Warren County
Other
2.0 MWOperating Warren, TNSoutheast Oct 2004
Edgeboro
Solar
2.0 MWOperating Middlesex, NJPJM Oct 20092011
Morris Road
Other
2.0 MWOperating Montgomery, PAPJM Apr 20092012
Solar project 639, Tooele County
Solar · Dugway Proving Ground
2.0 MWOperating Tooele, UTWest Jan 2015target 2016
East River 2 Uprate
Gas · Consolidated Edison Co. of NY
2.0 MWOperating NYNYISO Dec 2014
Esquatzel Project
Hydro · Green Energy Today, LLC
2.0 MWOperating Franklin, WAWest Nov 2010target 2011
Lilliwaup Falls Hydro Project
Hydro · Lilliwaup Falls Generating Company
2.0 MWOperating Mason, WAWest Aug 2014target 2014
Gas project GEN-2012-044, Crawford County
Gas
2.0 MWOperating Crawford, KSSPP Dec 20122013
Hydro project 398, Cascade County
Hydro
2.0 MWOperating Cascade, MTWest Nov 20202021
Beckjord Battery #2
Battery storage
2.0 MWOperating Clermont, OHPJM Apr 20132015
Spruce Mountain Wind Increase
Onshore wind
2.0 MWOperating Oxford, MEISO-NE Jan 2010target 2010
Fredrick County Regional LF
Other
2.0 MWOperating Frederick, VAPJM Mar 20082009
Other project W2-014, Philadelphia County
Other
2.0 MWOperating Philadelphia, PAPJM May 20102014
Fisher Solar Farm
Solar
2.0 MWOperating Hunterdon, NJPJM Jul 20102017
Onshore wind project G041, Pipestone County
Onshore wind
2.0 MWOperating Pipestone, MNMISO May 20002004
Reichs LF
Other
2.0 MWOperating Frederick, MDPJM Mar 20082009
Other project AF2-152, Charles County
Other
2.0 MWOperating Charles, MDPJM Mar 2020target 2021
Kinsley 2 Beaverbrook Solar
Solar
2.0 MWOperating Gloucester, NJPJM Feb 20192023
Other project G319, Martin County
Other
2.0 MWOperating Martin, MNMISO Mar 20032005
East River 1 Uprate
Gas · Consolidated Edison Co. of NY
2.0 MWOperating New York, NYNYISO Dec 20142019
Solar project 1030, Box Elder County
Solar · Nucor Corporation
2.0 MWOperating Box Elder, UTWest May 2018target 2018
Other project G348, Cass County
Other
2.0 MWOperating Cass, IAMISO May 2003
Belvidere SP
Solar
2.0 MWOperating Warren, NJPJM Jul 20082011
Solar project 666, Umatilla County
Solar · Pilot Rock Solar 1. LLC
2.0 MWOperating Umatilla, ORWest May 2015target 2025
Edgeboro
Solar
2.0 MWOperating Middlesex, NJPJM Oct 20092011
Other project AMALNAM, Canyon County
Other
2.0 MWOperating Canyon, IDWest
AC Landfill Energy Units 1-3
Other
2.0 MWOperating Atlantic, NJPJM Sep 20062007
Onshore wind project G241, Lincoln County
Onshore wind
2.0 MWOperating Lincoln, MNMISO Jul 20022002
Other project GI-0908, Beadle County
Other · Northwestern Energy
2.0 MWOperating Beadle, SDWest Feb 2009target 2009
Other project G067, Cass County
Other
2.0 MWOperating Cass, NDMISO Nov 20002004
Decatur Island Battery Storage
Battery storage
2.0 MWOperating San Juan, WAWest Nov 2019target 2018
Other project GI-0603, Jerauld County
Other · Prairie Ethanol LLC
2.0 MWOperating Jerauld, SDWest Apr 2006target 2006
Other project G0439, Lane County
Other
2.0 MWOperating Lane, ORWest Nov 2010target 2011
Titus Generating Station (Titus CT 4 and Titus CT 5)
Other
2.0 MWOperating Berks, PAPJM Sep 20192020
Other project G326, Marinette County
Other
2.0 MWOperating Marinette, WIMISO Mar 20032003
Rock Springs Units #1 & #2
Gas
2.0 MWOperating Cecil, MDPJM Aug 20132015
Solar project 444, Gallatin County
Solar
2.0 MWOperating Gallatin, MTWest Jul 20232024
Chalk Point CT 2
Gas
2.0 MWOperating Prince George's, MDPJM Mar 20202023
Gas project G341, Cottonwood County
Gas
2.0 MWOperating Cottonwood, MNMISO Nov 20012005
Worcester County Renewable Energy
Other
2.0 MWOperating Worcester, MDPJM Aug 20082012
Other project G140, Nobles County
Other
2.0 MWOperating Nobles, MNMISO Oct 2001
Other project G270, Nobles County
Other
2.0 MWOperating Nobles, MNMISO Dec 20022005
Salem County LF Generating Unit I
Other
2.0 MWOperating Salem, NJPJM Jul 20062008
Other project AF2-153, Charles County
Other
2.0 MWOperating Charles, MDPJM Mar 2020target 2021
Gas project 214, Sublette County
Gas · AntiCline Disposal, LLC
2.0 MWOperating Sublette, WYWest Apr 2008target 2009
Mantua Creek Frequency Regularor
Battery storage
2.0 MWOperating Gloucester, NJPJM May 20112013
Other project G142, Nobles County
Other
2.0 MWOperating Nobles, MNMISO Oct 20012001
Page 89 of 96

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)