United States › Grid › Interconnection queues › Minnesota

ONSHORE WIND · MISO

Onshore wind project G241, Lincoln County

Onshore wind project G241, Lincoln County is a 2.0 MW onshore wind request built and operating in the MISO interconnection queue, in Lincoln County, Minnesota.

Queue statusOperating
  1. PlanningQueued Jul 2002 (completed)
  2. ConsentedNov 2004 (completed)
  3. Construction (completed)
  4. OperatingSep 2002 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G241
Grid region
MISO (Midcontinent)
Connection point (POI)
Buffalo Ridge - Bravo 34.5kV
Location
Lincoln County, Minnesota
Technology
Wind: 2.0 MW
Total requested
2.0 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
30 July 2002
Agreement signed
10 November 2004
Proposed online date
September 2002
Came online
September 2002

Location

Marker shows the centre of Lincoln County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Lincoln County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem