United States › Grid › Interconnection queues › Minnesota

ONSHORE WIND · MISO

Onshore wind project J460, Lincoln County

Onshore wind project J460, Lincoln County is a 200 MW onshore wind request built and operating in the MISO interconnection queue, in Lincoln County, Minnesota.

Queue statusOperating
  1. PlanningQueued May 2015 (completed)
  2. ConsentedOct 2018 (completed)
  3. Construction (completed)
  4. OperatingSep 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J460
Grid region
MISO (Midcontinent)
Connection point (POI)
on Brookings - H081 345 kV line approx. 10 miles west of proposed substation
Location
Lincoln County, Minnesota
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
GIA
Queue status
Operational
Entered queue
18 May 2015
Agreement signed
2 October 2018
Proposed online date
September 2019
Came online
September 2019

Location

Marker shows the centre of Lincoln County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Lincoln County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem