SOLAR Β· PJM

Edgeboro

Edgeboro is a 2.0 MW solar request built and operating in the PJM interconnection queue, in Middlesex County, New Jersey, connecting to PSEG.

Queue statusOperating
  1. PlanningQueued Oct 2009 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingOct 2011 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
V3-058
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Brunswick 26.4kV
Location
Middlesex County, New Jersey
Technology
Solar: 2.0 MW
Total requested
2.0 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
30 October 2009
Proposed online date
October 2010
Came online
October 2011

Location

Marker shows the centre of Middlesex County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Middlesex County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem