United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in CAISO (California) — page 8

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown429188.6 GW
Active in queue188.6 GW429 requests
Agreement signed96.2 GW235 requests
Withdrawn2,186619.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

429 requests · page 8 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Nelson
Solar
104 MWIn study Nye, NVCAISO Apr 2023target 2031
Tioga Pass
Battery storage
103 MWIn study San Joaquin, CACAISO Apr 2023target 2028
Bonita Bateria
Battery storage
103 MWIn study Orange, CACAISO Apr 2023target 2029
Oakdale Storage
Battery storage
103 MWAgreement signed Stanislaus, CACAISO Apr 2021target 2029
Los Nietos
Battery storage
102 MWAgreement signed Orange, CACAISO Apr 2021target 2031
Cassia
Battery storage
102 MWIn study San Joaquin, CACAISO Apr 2023target 2031
Arges BESS
Battery storage
102 MWIn study Solano, CACAISO Apr 2021target 2029
Denali Energy Storage
Battery storage
102 MWAgreement signed San Joaquin, CACAISO Apr 2020target 2028
Pajaro Valley Storage
Battery storage
102 MWIn study San Diego, CACAISO Apr 2021target 2030
Kyan Solar
Solar
102 MWAgreement signed Kern, CACAISO May 2016target 2027
Droga
Battery storage
102 MWIn study Merced, CACAISO Apr 2023target 2028
Tokay Storage
Battery storage
102 MWAgreement signed Santa Clara, CACAISO Apr 2021target 2030
Double Springs Energy Storage
Battery storage
101 MWAgreement signed Calaveras, CACAISO Apr 2021target 2029
Sunbeam Storage
Battery storage
101 MWAgreement signed San Mateo, CACAISO Apr 2021target 2034
Eiger Energy Storage
Battery storage
101 MWIn study Kern, CACAISO Apr 2021target 2032
Peaceful Hollow BESS
Battery storage
100 MWAgreement signed Fresno, CACAISO Apr 2021target 2028
Keyhole Wind
Onshore wind
100 MWAgreement signed Kern, CACAISO Apr 2020target 2028
Golden Fields Solar
Battery storage
100 MWAgreement signed Kern, CACAISO Apr 2015target 2026
Sanborn Hybrid 4
Solar + storage
100 MWAgreement signed Kern, CACAISO Apr 2020target 2025
Azalea
Solar + storage
99.3 MWAgreement signed Kern, CACAISO Apr 2018target 2025
Noosa Energy Storage
Battery storage
99.0 MWAgreement signed San Joaquin, CACAISO Apr 2019target 2029
Solano 4 Wind
Onshore wind
92.4 MWAgreement signed Solano, CACAISO Apr 2018target 2025
Chalan Solar
Solar + storage
91.8 MWAgreement signed Kern, CACAISO Apr 2018target 2026
Fresno Cogeneration Expansion Project
Gas
91.8 MWAgreement signed Fresno, CACAISO Mar 20052007
Redwood Solar Farm
Solar
90.0 MWAgreement signed Kern, CACAISO Mar 2011target 2024
Sunshine Valley Solar 1
Solar + storage
90.0 MWAgreement signed Nye, NVCAISO Apr 2013target 2026
Sand Hill C
Onshore wind
84.3 MWAgreement signed Alameda, CACAISO May 2017target 2027
Gonzaga Wind Farm
Onshore wind
80.0 MWAgreement signed Merced, CACAISO May 2017target 2026
Valetudo Energy Storage
Battery storage
79.6 MWIn study Madera, CACAISO Apr 2021target 2028
Montezuma (High Winds III)
Wind + storage
76.0 MWAgreement signed Solano, CACAISO Nov 20032010
Palmetto Energy Storage
Battery storage
75.6 MWIn study Alameda, CACAISO Apr 2021target 2030
Hummingbird Energy Storage
Battery storage
75.0 MWAgreement signed Santa Clara, CACAISO Apr 2018target 2025
Willow Springs Solar 4
Battery storage
75.0 MWAgreement signed Kern, CACAISO Apr 2015target 2026
Rosemary
Solar + storage
72.3 MWAgreement signed Fresno, CACAISO Apr 2020target 2028
Tarragon Hybrid
Solar + storage
71.9 MWIn study Fresno, CACAISO Apr 2021target 2028
Hammerhead Storage
Battery storage
71.3 MWIn study San Diego, CACAISO Apr 2021target 2030
Fallbrook Energy Storage
Battery storage
69.6 MWAgreement signed San Diego, CACAISO Apr 2015target 2026
Off Stream Water Storage
Battery storage
68.9 MWIn study Colusa, CACAISO Apr 2023target 2030
Box
Solar
63.4 MWIn study Riverside, CACAISO Apr 2023target 2029
Little Hill
Battery storage
63.1 MWIn study San Bernardino, CACAISO Apr 2023target 2031
Mulqueeney Ranch Wind 2
Onshore wind
62.5 MWAgreement signed Alameda, CACAISO Apr 2018target 2026
Angela
Solar + storage
60.0 MWAgreement signed Tulare, CACAISO Apr 2018target 2025
Prospect Energy Storage
Battery storage
58.8 MWPaused / redesign Sacramento, CACAISO Apr 2018target 2028
Camino Solar
Solar + storage
58.3 MWAgreement signed Kern, CACAISO May 2017target 2027
Bottle Rock Power
Other
56.9 MWAgreement signed Lake, CACAISO Sep 20052007
Mayacamas Geothermal
Geothermal
53.0 MWIn study Sonoma, CACAISO Apr 2021target 2030
Scafell Storage
Battery storage
52.0 MWIn study San Diego, CACAISO Apr 2020target 2029
Geranium Energy Storage
Battery storage
51.4 MWIn study San Diego, CACAISO Apr 2021target 2029
Orleans
Solar + storage
51.1 MWAgreement signed Fresno, CACAISO Apr 2021target 2029
Ventasso Energy Storage
Battery storage
50.8 MWAgreement signed San Diego, CACAISO Apr 2019target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)