🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Tarragon Hybrid

Tarragon Hybrid is a 71.9 MW solar + storage request in interconnection study in the CAISO interconnection queue, in Fresno County, California, connecting to PGAE.

Queue statusIn planning
  1. PlanningQueued Apr 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
1975
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Crescent 70 kV
Location
Fresno County, California
Technology
Solar: 36.0 MW · Battery: 36.0 MW
Total requested
71.9 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
15 April 2021
Proposed online date
June 2028

Location

Marker shows the centre of Fresno County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Fresno County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem