Requests shown32874.4 GW
Active in queue74.4 GW328 requests
Agreement signed5,506 MW27 requests
Withdrawn1,273328.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

328 requests · page 7 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Surplus; J893 (Searcy Solar)
Other
10.0 MWIn study MISO Jun 20202022
Other project AI2-025, New Castle County
Other
10.0 MWIn study New Castle, DEPJM Dec 2022target 2026
Other project J963, Cedar County
Other
9.0 MWAgreement signed Cedar, IAMISO Mar 2018target 2017
Other project J3763, Wayne County
Other
7.5 MWIn study Wayne, MIMISO Apr 2024target 2026
Surplus; Gibson Generating Station
Other
7.5 MWIn study MISO Jun 2020
Other project G085, Jackson County
Other
7.0 MWIn study Jackson, WIMISO Mar 2001target 2005
Battery addition
Other
6.7 MWAgreement signed Franklin, MAISO-NE Aug 2021target 2027
Other project AI1-053, Mercer County
Other
6.6 MWIn study Mercer, PAPJM Jun 2022target 2022
Other project G177, Lyon County
Other
5.0 MWAgreement signed Lyon, MNMISO Mar 2002target 2004
Other project Q394, Maricopa County
Other
5.0 MWIn study Maricopa, AZWest Mar 2021target 2021
Other project hist_q71, Stevens County
Other
4.5 MWPaused / redesign Stevens, WAWest
Other project AH2-001, Susquehanna County
Other
3.6 MWIn study Susquehanna, PAPJM Oct 2021target 2023
Surplus; Petersburg
Other
3.0 MWIn study Pike, INMISO May 2022target 2023
Other project 894253, Cleveland County
Other
2.8 MWUnder construction Cleveland, NCSoutheast Jan 2000
Other project 897777, Wake County
Other
2.0 MWUnder construction Wake, NCSoutheast Jun 2023target 2025
Other project J953, Johnson County
Other
2.0 MWAgreement signed Johnson, IAMISO Mar 2018target 2006
Other project G0710, Flathead County
Other
1.6 MWIn study Flathead, MTWest Nov 2021target 2022
Other project J646, Macomb County
Other
1.6 MWUnder construction Macomb, MIMISO Jun 2016target 2010
Other project Company MN, Lyon County
Other
1.3 MWAgreement signed Lyon, NVWest Dec 2021target 2022
Other project J258, Stearns County
Other
1.0 MWAgreement signed Stearns, MNMISO Oct 2012target 2013
Other project 15, Skagit County
Other
0.8 MWIn study Skagit, WAWest Mar 2008target 2008
Other project L008, Delaware County
Other
-4.0 MWIn study Delaware, OHMISO Nov 2004target 2004
Other project L006, Otsego County
Other
-5.0 MWIn study Otsego, MIMISO Sep 2004target 2005
Other project L010
Other
-8.0 MWIn study MIMISO Apr 2005target 2005
Other project L003, Lenawee County
Other
-10.0 MWIn study Lenawee, MIMISO May 2004
Other project L009, Jackson County
Other
-11.0 MWIn study Jackson, MNMISO Jan 2005target 2005
Other project L004, Williams County
Other
-22.0 MWIn study Williams, OHMISO Jul 2004target 2009
Other project L002, Scott County
Other
-28.0 MWIn study Scott, MNMISO May 2004target 2015
Page 7 of 7

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)