United States › Grid › Interconnection queues › Michigan
OTHER · MISOOther project J3763, Wayne County
Other project J3763, Wayne County is a 7.5 MW other request in interconnection study in the MISO interconnection queue, in Wayne County, Michigan, connecting to ITC.
Queue statusIn planning
- PlanningQueued Apr 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3763
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC
- Connection point (POI)
- DBGEN GIS
- Location
- Wayne County, Michigan
- Technology
- Other: 7.5 MW
- Total requested
- 7.5 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Active
- Entered queue
- 18 April 2024
- Proposed online date
- June 2026
Location
Marker shows the centre of Wayne County; the queue data does not give exact sites.
Other requests in Wayne County
- Gas project J1798, Wayne CountyGas · 25.0 MW · agreement signed
- Gas project J1262, Wayne CountyGas · 25.0 MW · agreement signed
- Battery storage project J3872, Wayne CountyBattery storage · 350 MW · in study
- Replacing 220 MW of coal generation with BESS; Trenton Channel 9Other · 220 MW · in study
- Battery storage project J2991, Wayne CountyBattery storage · 200 MW · in study
- Battery storage project J1902, Wayne CountyBattery storage · 200 MW · in study
- Battery storage project J1900, Wayne CountyBattery storage · 200 MW · in study
- Gas project G023, Wayne CountyGas · 710 MW · built
- Gas project G038, Wayne CountyGas · 360 MW · built
- Gas project G026, Wayne CountyGas · 240 MW · built
- Gas project J440, Wayne CountyGas · 52.0 MW · built
- Gas project G095, Wayne CountyGas · 644 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem