Gas project J440, Wayne County

Gas project J440, Wayne County is a 52.0 MW gas request built and operating in the MISO interconnection queue, in Wayne County, Michigan.

Queue statusOperating
  1. PlanningQueued Mar 2015 (completed)
  2. ConsentedFeb 2017 (completed)
  3. Construction (completed)
  4. OperatingJan 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J440
Grid region
MISO (Midcontinent)
Connection point (POI)
Consumers DIGG 230 kV substation
Location
Wayne County, Michigan
Technology
Gas: 52.0 MW
Total requested
52.0 MW
Study phase
DPP - SIS
Queue status
Operational
Entered queue
16 March 2015
Agreement signed
23 February 2017
Proposed online date
January 2016
Came online
January 2016

Location

Marker shows the centre of Wayne County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Wayne County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem