United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 61

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 61 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Bayonne Energy Storage II
Battery storage · AMBAR POWER HOLDCO LLC
400 MWWithdrawn / abandoned Hudson, NJNYISO Oct 2024
Onshore wind project GI-2008-24, Huerfano County
Onshore wind
400 MWWithdrawn / abandoned Huerfano, COWest Oct 2008target 2012
Solar + storage project Q72, San Bernardino County
Solar + storage
400 MWWithdrawn / abandoned San Bernardino, CAWest Jul 2019target 2021
Coal project GEN-2001-040N, Dawson County
Coal
400 MWWithdrawn / abandoned Dawson, NESPP Jan 2002
Pavion
Battery storage
400 MWWithdrawn / abandoned San Diego, CACAISO Apr 2021target 2026
Coal project G293, Buffalo County
Coal
400 MWWithdrawn / abandoned Buffalo, WIMISO Dec 2002target 2004
Solar project J1011, Kenosha County
Solar
400 MWWithdrawn / abandoned Kenosha, WIMISO Mar 2018target 2022
Onshore wind project AE2-232, Atlantic County
Onshore wind
400 MWWithdrawn / abandoned Atlantic, NJPJM Mar 2019target 2023
Onshore wind project GI-2008-8, Sedgwick County
Onshore wind
400 MWWithdrawn / abandoned Sedgwick, COWest Jun 2008target 2010
Solar + storage project G0890, Lane County
Solar + storage
400 MWWithdrawn / abandoned Lane, ORWest Jun 2023target 2030
Onshore wind project Q366, Coconino County
Onshore wind
400 MWWithdrawn / abandoned Coconino, AZWest Jan 2021target 2024
Solar + storage project AG2-437, Greensville County
Solar + storage
400 MWWithdrawn / abandoned Greensville, VAPJM Mar 2021target 2023
Solar + storage project GEN-2023-212, Bowie County
Solar + storage
400 MWWithdrawn / abandoned Bowie, TXSPP Oct 2023target 2027
Solar + storage project 20220601002, Richland County
Solar + storage
400 MWWithdrawn / abandoned Richland, SCSoutheast target 2026
Solar + storage project Q12, Pinal County
Solar + storage
400 MWWithdrawn / abandoned Pinal, AZWest Jan 2019target 2023
Solar project GEN-2023-236, Lea County
Solar
400 MWWithdrawn / abandoned Lea, NMSPP Oct 2023target 2030
Onshore wind project G0958, Wasco County
Onshore wind
400 MWWithdrawn / abandoned Wasco, ORWest Oct 2023target 2027
Fitzgibbons Solar
Solar + storage
400 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2025
Battery storage project Q94, Pinal County
Battery storage
400 MWWithdrawn / abandoned Pinal, AZWest Apr 2022target 2025
Other project 82, Haywood County
Other
400 MWWithdrawn / abandoned Haywood, TNSoutheast Mar 2000
Solar project J3540, Monroe County
Solar
400 MWWithdrawn / abandoned Monroe, ARMISO Apr 2024target 2028
Onshore wind project GI-2017-43, Huerfano County
Onshore wind
400 MWWithdrawn / abandoned Huerfano, COWest Nov 2017target 2020
Solar project GEN-2024-156, Howard County
Solar
400 MWWithdrawn / abandoned Howard, ARSPP Mar 2025target 2029
Battery storage project GEN-2019-064, Swisher County
Battery storage
400 MWWithdrawn / abandoned Swisher, TXSPP May 2019target 2024
Fort Concho Wind Farm
Onshore wind · Horizon Wind Energy
400 MWWithdrawn / abandoned ERCOT Jun 2007target 2050
Wind + storage project 23-223, Washington County
Wind + storage
400 MWWithdrawn / abandoned Washington, ORWest Mar 2023target 2028
Battery storage project 628, Martin County
Battery storage · FPL
400 MWWithdrawn / abandoned Martin, FLSoutheast Jan 2024target 2031
Gas project U4-032, Armstrong County
Gas
400 MWWithdrawn / abandoned Armstrong, PAPJM Dec 2008target 2013
Wellhead Power Kern 3
Gas
400 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2015
Solar + storage project GEN-2023-050, Labette County
Solar + storage
400 MWWithdrawn / abandoned Labette, KSSPP Oct 2023target 2028
Gas project 976884, Cherokee County
Gas
400 MWWithdrawn / abandoned Cherokee, SCSoutheast Jun 2025
Onshore wind project J627, Meeker County
Onshore wind
400 MWWithdrawn / abandoned Meeker, MNMISO May 2016target 2019
Solar project 2, Sacramento County
Solar
400 MWWithdrawn / abandoned Sacramento, CAWest Oct 2019target 2023
Solar project Q344
Solar
400 MWWithdrawn / abandoned AZWest Mar 2020target 2021
Onshore wind project G972, Fayette County
Onshore wind
400 MWWithdrawn / abandoned Fayette, IAMISO Feb 2008target 2010
Solar + storage project J3105, Amite County
Solar + storage
400 MWWithdrawn / abandoned Amite, MSMISO Sep 2022target 2025
Los Vientos Phase III
Onshore wind · Duke Energy Generation Services
400 MWWithdrawn / abandoned ERCOT Oct 2011target 2050
Solar project GI-2017-35, Pueblo County
Solar
400 MWWithdrawn / abandoned Pueblo, COWest Sep 2017target 2020
Solar + storage project GI-2022-10, Pueblo County
Solar + storage
400 MWWithdrawn / abandoned Pueblo, COWest Apr 2022target 2025
Battery storage project J3022, Taylor County
Battery storage
400 MWWithdrawn / abandoned Taylor, IAMISO Sep 2022target 2026
Baker Ranch
Onshore wind · Higher Power Energy, LLC
400 MWWithdrawn / abandoned ERCOT Oct 2007target 2014
Solar + storage project Q18, Pinal County
Solar + storage
400 MWWithdrawn / abandoned Pinal, AZWest May 2021target 2025
Onshore wind project J626, Meeker County
Onshore wind
400 MWWithdrawn / abandoned Meeker, MNMISO May 2016target 2019
Battery storage project J3728, Franklin County
Battery storage
400 MWWithdrawn / abandoned Franklin, ILMISO Apr 2024target 2028
Solar + storage project IC-862, Decatur County
Solar + storage
400 MWWithdrawn / abandoned Decatur, GASoutheast Apr 2020target 2025
Star Generation
Gas
400 MWWithdrawn / abandoned San Diego, CACAISO Apr 2007target 2010
Onshore wind project J628, Grand Forks County
Onshore wind
400 MWWithdrawn / abandoned Grand Forks, NDMISO Jun 2017target 2022
Panoche Valley Solar Farm Expansion
Solar
400 MWWithdrawn / abandoned San Benito, NVCAISO Feb 2010target 2013
Battery storage project Q436, Coconino County
Battery storage
400 MWWithdrawn / abandoned Coconino, AZWest Sep 2021target 2025
Other project G0896, Lane County
Other
400 MWWithdrawn / abandoned Lane, ORWest Jun 2023target 2030
Page 61 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)