BATTERY STORAGE Β· CAISO

Pavion

Pavion is a 400 MW battery storage request withdrawn in the CAISO interconnection queue, in San Diego County, California, connecting to SDGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedDec 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2163
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Talega Substation 230 kV
Location
San Diego County, California
Technology
Battery: 400 MW
Total requested
400 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
15 April 2021
Proposed online date
June 2026
Withdrawn
December 2022

Location

Marker shows the centre of San Diego County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in San Diego County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem