Interconnection queue in MISO (Midcontinent) (2024 requests) β€” page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown29062.9 GW
Active in queue62.9 GW290 requests
Agreement signed0.0 MW0 requests
Withdrawn41178.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

290 requests Β· page 6 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project J3983, Gibson County
Solar + storage
100 MWIn study Gibson, INMISO Oct 2024target 2030
Solar project J3917, Columbia County
Solar
100 MWIn study Columbia, ARMISO Nov 2024target 2029
Solar project J3899, Putnam County
Solar
100 MWIn study Putnam, ILMISO Dec 2024target 2027
Battery storage project J3344, Knox County
Battery storage
100 MWIn study Knox, ILMISO Apr 2024target 2028
Solar project J3828, Lapeer County
Solar
100 MWIn study Lapeer, MIMISO Apr 2024target 2028
Solar project J3379, Johnson County
Solar
100 MWIn study Johnson, ILMISO Apr 2024target 2028
Battery storage project J3485, Huron County
Battery storage
100 MWIn study Huron, MIMISO Apr 2024target 2028
Onshore wind project J3469, Marathon County
Onshore wind
100 MWIn study Marathon, WIMISO Apr 2024target 2026
Solar project J3481, Grant County
Solar
100 MWIn study Grant, ARMISO Apr 2024target 2027
Battery storage project J3421, Huron County
Battery storage
100 MWIn study Huron, MIMISO Apr 2024target 2028
Surplus; J385
Other
100 MWIn study Chisago, MNMISO Jul 2024target 2026
Onshore wind project J3341, Vermilion County
Onshore wind
100 MWIn study Vermilion, ILMISO Apr 2024target 2028
Battery storage project J3861, Branch County
Battery storage
100 MWIn study Branch, MIMISO Dec 2024target 2028
Battery storage project J3268, Gratiot County
Battery storage
100 MWIn study Gratiot, MIMISO Apr 2024target 2027
Solar project J3470, Tuscola County
Solar
100 MWIn study Tuscola, MIMISO Apr 2024target 2027
Solar project J3466, Winnebago County
Solar
100 MWIn study Winnebago, WIMISO Apr 2024target 2028
Surplus; J758
Other
100 MWIn study Calhoun, MIMISO Aug 2024target 2027
Replacing 95 MW of coal with BESS; Meramec 1, 2, 3, 4
Other
98.8 MWIn study St. Louis, MOMISO Dec 2024target 2025
Solar project J3777, Cheboygan County
Solar
91.8 MWIn study Cheboygan, MIMISO Apr 2024target 2028
Solar project J3953, Faulkner County
Solar
90.0 MWIn study Faulkner, ARMISO Nov 2024target 2028
Gas project J3870, Vigo County
Gas
87.0 MWIn study Vigo, INMISO Dec 2024target 2002
Surplus; J1224/J1329
Other
85.1 MWIn study Washtenaw, MIMISO Oct 2024target 2028
Solar project J3914, Jefferson Davis Parish County
Solar
85.0 MWIn study Jefferson Davis Parish, LAMISO Oct 2024target 2030
Solar project J3988, Morehouse Parish County
Solar
85.0 MWIn study Morehouse Parish, LAMISO Oct 2024target 2030
Solar project J3653, Washtenaw County
Solar
80.0 MWIn study Washtenaw, MIMISO Apr 2024target 2028
Surplus; Old Gold
Other
80.0 MWIn study Worth, IAMISO Jun 2024target 2029
Solar + storage project J3630, East Feliciana Parish County
Solar + storage
77.0 MWIn study East Feliciana Parish, LAMISO Apr 2024target 2028
Solar project J3590, Humphreys County
Solar
75.0 MWIn study Humphreys, MSMISO Apr 2024target 2028
Solar project J3529, Mahnomen County
Solar
64.0 MWIn study Mahnomen, MNMISO May 2024target 2028
Onshore wind project J3592, Sunflower County
Onshore wind
57.0 MWIn study Sunflower, MSMISO Apr 2024target 2028
Replacing 55 MW with 29 MW Natural Gas/Fuel Oil; Blue Lake Unit 3
Gas
55.0 MWIn study Scott, MNMISO May 2024target 2025
Surplus; G905
Other
50.0 MWIn study Midland, MIMISO Aug 2024target 2026
Solar project J2891, Kenosha County
Solar
50.0 MWIn study Kenosha, WIMISO Jan 2024target 2026
Onshore wind project J2312, Putnam County
Onshore wind
47.9 MWIn study Putnam, ILMISO Oct 2024target 2024
Onshore wind project J3336, Tuscola County
Onshore wind
41.8 MWIn study Tuscola, MIMISO Apr 2024target 2027
Solar project J3818, Shelby County
Solar
40.0 MWIn study Shelby, ILMISO Jun 2024target 2028
Surplus; G291
Other
21.0 MWIn study MISO Sep 2024target 2026
Other project J3763, Wayne County
Other
7.5 MWIn study Wayne, MIMISO Apr 2024target 2026
Gas project J3756, Marquette County
Gas
4.2 MWIn study Marquette, MIMISO Apr 2024target 2019
Gas project J3800, Baraga County
Gas
1.8 MWIn study Baraga, MIMISO Apr 2024target 2019
Page 6 of 6

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)