United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 59

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,226638.1 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,226 requests · page 59 of 105
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AG1-385, Washington County
Solar
20.0 MWWithdrawn / abandoned Washington, PAPJM Sep 2020target 2022
Thomas Ridge Solar
Solar
20.0 MWWithdrawn / abandoned Snyder, PAPJM Mar 2019target 2024
Solar project AG1-346, Shenandoah County
Solar · Ginger Gold Solar LLC
20.0 MWWithdrawn / abandoned Shenandoah, VAPJM Sep 2020target 2022
Solar project AH1-113, Brown County
Solar
20.0 MWWithdrawn / abandoned Brown, OHPJM Aug 2021target 2023
Other project V3-063, City Of Martinsville County
Other
20.0 MWWithdrawn / abandoned City Of Martinsville, VAPJM Oct 2009target 2012
Solar project AH1-420, City Of Chesapeake County
Solar
20.0 MWWithdrawn / abandoned City Of Chesapeake, VAPJM Sep 2021target 2023
Solar project AH1-380, Worcester County
Solar · Forest Lane Solar, LLC
20.0 MWWithdrawn / abandoned Worcester, MDPJM Feb 2025target 2024
Solar project AI1-073, Franklin County
Solar
20.0 MWWithdrawn / abandoned Franklin, PAPJM Jun 2022target 2027
Solar project AE1-199, Ogle County
Solar
20.0 MWWithdrawn / abandoned Ogle, ILPJM Sep 2018target 2019
Solar project AF1-334, Berks County
Solar
20.0 MWWithdrawn / abandoned Berks, PAPJM Sep 2019target 2021
Solar project AG2-387, Rockingham County
Solar
20.0 MWWithdrawn / abandoned Rockingham, VAPJM Mar 2021target 2023
Solar project W1-021, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, NJPJM Feb 2010target 2011
GCC Realty
Onshore wind
20.0 MWWithdrawn / abandoned Schuylkill, PAPJM Nov 2006target 2015
Battery storage project Y1-078, Cook County
Battery storage
20.0 MWWithdrawn / abandoned Cook, ILPJM Apr 2012target 2012
Solar project X1-028, Franklin County
Solar
20.0 MWWithdrawn / abandoned Franklin, PAPJM Mar 2011target 2012
Solar project AF1-214, Centre County
Solar
20.0 MWWithdrawn / abandoned Centre, PAPJM Sep 2019target 2022
Solar + storage project AG1-273, Charlotte County
Solar + storage · CV-Tollhouse LLC
20.0 MWWithdrawn / abandoned Charlotte, VAPJM Sep 2020target 2022
Solar + storage project AF2-310, Garrett County
Solar + storage
20.0 MWWithdrawn / abandoned Garrett, MDPJM Mar 2020target 2022
Solar project AA2-163, Sussex County
Solar
20.0 MWWithdrawn / abandoned Sussex, VAPJM Apr 2015target 2015
Solar project AC2-097, Pulaski County
Solar
20.0 MWWithdrawn / abandoned Pulaski, VAPJM Mar 2017target 2018
Solar project X4-017, Wicomico County
Solar
20.0 MWWithdrawn / abandoned Wicomico, MDPJM Nov 2011target 2017
Solar project AE1-009, Fluvanna County
Solar
20.0 MWWithdrawn / abandoned Fluvanna, VAPJM Apr 2018target 2020
Battery storage project AB1-074, Philadelphia County
Battery storage
20.0 MWWithdrawn / abandoned Philadelphia, PAPJM Sep 2015target 2016
Solar project AG2-588, Warren County
Solar
20.0 MWWithdrawn / abandoned Warren, NJPJM Mar 2021target 2024
Solar project AG1-382, Cambria County
Solar
20.0 MWWithdrawn / abandoned Cambria, PAPJM Sep 2020target 2022
Solar project W1-118, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, NJPJM Apr 2010target 2011
Solar project AB2-062, Orange County
Solar
20.0 MWWithdrawn / abandoned Orange, VAPJM Mar 2016target 2018
Solar + storage project AG1-274, Charlotte County
Solar + storage · CV-Tollhouse LLC
20.0 MWWithdrawn / abandoned Charlotte, VAPJM Sep 2020target 2022
Solar project AI2-031, Sussex County
Solar
20.0 MWWithdrawn / abandoned Sussex, VAPJM Jan 2023target 2024
Onshore wind project W3-039, Hudson County
Onshore wind
20.0 MWWithdrawn / abandoned Hudson, NJPJM Aug 2010target 2012
Solar project W4-035, Clinton County
Solar
20.0 MWWithdrawn / abandoned Clinton, OHPJM Dec 2010target 2012
Solar project W4-028, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Dec 2010target 2011
Solar project AF1-151, Franklin County
Solar
20.0 MWWithdrawn / abandoned Franklin, PAPJM Sep 2019target 2022
Solar project AB2-164, Accomack County
Solar
20.0 MWWithdrawn / abandoned Accomack, VAPJM Apr 2016target 2018
Solar project AH1-423, Champaign County
Solar
20.0 MWWithdrawn / abandoned Champaign, OHPJM Sep 2021target 2024
Charles City Solar
Solar
20.0 MWWithdrawn / abandoned VAPJM Oct 2015target 2019
Cambria Energy
Battery storage
20.0 MWWithdrawn / abandoned Cambria, PAPJM Dec 2019target 2022
Solar project AG2-033, Auglaize County
Solar
20.0 MWWithdrawn / abandoned Auglaize, OHPJM Nov 2020target 2023
Churchill Storage Solutions LLC
Battery storage · Churchill Storage Solutions LLC
20.0 MWWithdrawn / abandoned City Of Hopewell, VAPJM Feb 2025target 2023
Solar project AH1-074, Huron County
Solar
20.0 MWWithdrawn / abandoned Huron, OHPJM Jul 2021target 2024
Solar + storage project AG1-279, Luzerne County
Solar + storage · LU-Tank LLC
20.0 MWWithdrawn / abandoned Luzerne, PAPJM Sep 2020target 2022
Battery storage project AF2-351, Kankakee County
Battery storage · Deriva Energy Solar, LLC
20.0 MWWithdrawn / abandoned Kankakee, ILPJM Mar 2020target 2023
Catoctin Furnace Solar Facility
Solar
20.0 MWWithdrawn / abandoned Frederick, MDPJM Aug 2016target 2018
Solar project W2-101, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Jul 2010target 2017
Onshore wind project S53, Bureau County
Onshore wind
20.0 MWWithdrawn / abandoned Bureau, ILPJM May 2007target 2008
Solar project W4-100, Hunterdon County
Solar
20.0 MWWithdrawn / abandoned Hunterdon, NJPJM Jan 2011target 2012
Grand View Solar I
Solar · PD Solar 2 LLC
20.0 MWWithdrawn / abandoned Berks, PAPJM Sep 2021target 2024
Brookview Solar I
Solar
20.0 MWWithdrawn / abandoned Adams, PAPJM Apr 2018target 2025
Solar project W1-117, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, NJPJM Apr 2010target 2011
Solar project AF2-017, Pike County
Solar
20.0 MWWithdrawn / abandoned Pike, KYPJM Oct 2019target 2021
Page 59 of 105

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)