United States β€Ί Grid β€Ί Interconnection queues β€Ί Virginia

SOLAR Β· PJM

Solar project AG2-387, Rockingham County

Solar project AG2-387, Rockingham County is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Rockingham County, Virginia, connecting to Dominion.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandonedJun 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-387
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Cargill 115 kV (SVEC)
Location
Rockingham County, Virginia
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
29 March 2021
Proposed online date
October 2023
Withdrawn
June 2023

Location

Marker shows the centre of Rockingham County; the queue data does not give exact sites.

Power plants in Virginia Β· Transmission lines in Virginia

Other requests in Rockingham County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem