ONSHORE WIND Β· PJMGCC Realty
GCC Realty is a 20.0 MW onshore wind request withdrawn in the PJM interconnection queue, in Schuylkill County, Pennsylvania, connecting to PPL.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2006 (completed)
- Withdrawn / abandonedJun 2015 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- R43
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PPL
- Connection point (POI)
- Frackville - Hauto #3
- Location
- Schuylkill County, Pennsylvania
- Technology
- Wind: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Withdrawn
- Entered queue
- 27 November 2006
- Proposed online date
- June 2015
- Withdrawn
- June 2015
Location
Marker shows the centre of Schuylkill County; the queue data does not give exact sites.
Power plants in Pennsylvania Β· Transmission lines in Pennsylvania
Other requests in Schuylkill County
- Solar + storage project AH2-256, Schuylkill CountySolar + storage Β· 50.0 MW Β· in study
- Locust Ridge II WFOnshore wind Β· 100 MW Β· built
- Locust Ridge WFOnshore wind Β· 24.0 MW Β· built
- Commonwealth LFOther Β· 10.5 MW Β· built
- Guilford Mills LFOther Β· 8.0 MW Β· built
- Locust Ridge WFOnshore wind Β· 2.0 MW Β· built
- Locust Ridge WFOnshore wind Β· 1.3 MW Β· built
- Coal project Q89, Schuylkill CountyCoal Β· 750 MW Β· withdrawn
- Hydro project AE1-058, Schuylkill CountyHydro Β· 500 MW Β· withdrawn
- Hydro project AE2-135, Schuylkill CountyHydro Β· 500 MW Β· withdrawn
- Gas project Y2-015, Schuylkill CountyGas Β· 344 MW Β· withdrawn
- Gas project Y2-063, Schuylkill CountyGas Β· 344 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem