United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 51

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,226638.1 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,226 requests · page 51 of 105
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AB2-083, Ross County
Solar
40.0 MWWithdrawn / abandoned Ross, OHPJM Apr 2016target 2017
Battery storage project AG1-150, Accomack County
Battery storage
40.0 MWWithdrawn / abandoned Accomack, VAPJM Sep 2020target 2021
Solar project AH1-156, Bourbon County
Solar
40.0 MWWithdrawn / abandoned Bourbon, KYPJM Aug 2021target 2026
Solar + storage project AG2-277, Fayette County
Solar + storage
40.0 MWWithdrawn / abandoned Fayette, OHPJM Mar 2021target 2023
Solar + storage project AH1-421, Champaign County
Solar + storage
40.0 MWWithdrawn / abandoned Champaign, OHPJM Sep 2021target 2024
Coal project N28, Cambria County
Coal
40.0 MWWithdrawn / abandoned Cambria, PAPJM Jan 2005target 2007
Solar + storage project AH2-276, Pike County
Solar + storage
40.0 MWWithdrawn / abandoned Pike, KYPJM Mar 2022target 2024
Solar + storage project AH1-614, Clermont County
Solar + storage
40.0 MWWithdrawn / abandoned Clermont, OHPJM Sep 2021target 2025
Solar project AH1-058, Morrow County
Solar
40.0 MWWithdrawn / abandoned Morrow, OHPJM Jul 2021target 2024
Solar project AC2-166, Dekalb County
Solar
40.0 MWWithdrawn / abandoned Dekalb, ILPJM Mar 2017target 2019
Battery storage project AH1-369, Tucker County
Battery storage
40.0 MWWithdrawn / abandoned Tucker, WVPJM Sep 2021target 2023
Battery storage project AG2-187, Amherst County
Battery storage
40.0 MWWithdrawn / abandoned Amherst, VAPJM Feb 2021target 2024
Scout Energy Storage
Battery storage
40.0 MWWithdrawn / abandoned Accomack, VAPJM Jan 2020target 2021
Battery storage project AF2-394, Adams County
Battery storage · Bison Meadows Wind Project, LLC
40.0 MWWithdrawn / abandoned Adams, ILPJM Mar 2020target 2024
Solar + storage project AG2-546, Grant County
Solar + storage
40.0 MWWithdrawn / abandoned Grant, INPJM Mar 2021target 2023
Solar project AG1-458, Washington County
Solar
40.0 MWWithdrawn / abandoned Washington, MDPJM Sep 2020target 2023
Solar project AF2-067, Preble County
Solar
40.0 MWWithdrawn / abandoned Preble, OHPJM Jan 2020target 2022
Battery storage project AG2-338, Sussex County
Battery storage · Cassius Blue Solar LLC
40.0 MWWithdrawn / abandoned Sussex, VAPJM Apr 2025target 2024
Solar + storage project AI1-140, Wayne County
Solar + storage
40.0 MWWithdrawn / abandoned Wayne, INPJM Sep 2022target 2025
Solar project AG2-549, Hardin County
Solar
40.0 MWWithdrawn / abandoned Hardin, KYPJM Mar 2021target 2022
Solar project AF1-313, Delaware County
Solar
40.0 MWWithdrawn / abandoned Delaware, INPJM Sep 2019target 2022
Battery storage project AH1-352, Campbell County
Battery storage · Altavista Solar, LLC
40.0 MWWithdrawn / abandoned Campbell, VAPJM Sep 2021target 2023
Solar project AF2-094, Huntington County
Solar
40.0 MWWithdrawn / abandoned Huntington, INPJM Feb 2020target 2022
Battery storage project AH1-428, Boone County
Battery storage · ACE Development Company, LLC
40.0 MWWithdrawn / abandoned Boone, KYPJM Sep 2021target 2026
Solar project AE2-044, Edgecombe County
Solar
40.0 MWWithdrawn / abandoned Edgecombe, NCPJM Jan 2019target 2019
Battery storage project AE2-188, Culpeper County
Battery storage
40.0 MWWithdrawn / abandoned Culpeper, VAPJM Mar 2019target 2020
Bartonsville Energy Facility
Solar
40.0 MWWithdrawn / abandoned Frederick, VAPJM Sep 2020target 2023
Solar project AB2-150, Greensville County
Solar
40.0 MWWithdrawn / abandoned Greensville, VAPJM Apr 2016target 2017
Onshore wind project N29, Garrett County
Onshore wind
40.0 MWWithdrawn / abandoned Garrett, MDPJM Jan 2005target 2008
Solar project AG2-627, Gloucester County
Solar · South Harrison Solar, LLC
40.0 MWWithdrawn / abandoned Gloucester, NJPJM Mar 2025target 2024
Battery storage project AH1-640, Campbell County
Battery storage
40.0 MWWithdrawn / abandoned Campbell, VAPJM Sep 2021target 2025
Solar + storage project AH1-219, Logan County
Solar + storage
39.9 MWWithdrawn / abandoned Logan, OHPJM Sep 2021target 2025
Onshore wind project K03, Luzerne County
Onshore wind
39.6 MWWithdrawn / abandoned Luzerne, PAPJM Mar 2003
Gas project D25, New Castle County
Gas
39.0 MWWithdrawn / abandoned New Castle, DEPJM Jul 2000
Highland New Wind
Onshore wind
39.0 MWWithdrawn / abandoned Highland, VAPJM Sep 2004target 2021
Solar + storage project AI1-108, Rockingham County
Solar + storage
38.5 MWWithdrawn / abandoned Rockingham, VAPJM Aug 2022target 2026
Solar project AE2-277, Mercer County
Solar
38.2 MWWithdrawn / abandoned Mercer, PAPJM Mar 2019
Solar project AE1-239, Mercer County
Solar
38.2 MWWithdrawn / abandoned Mercer, PAPJM Sep 2018target 2021
Solar + storage project AG2-590, Huntingdon County
Solar + storage · North Corners Energy, LLC
38.2 MWWithdrawn / abandoned Huntingdon, PAPJM Mar 2021target 2024
Solar project AH1-020, Fluvanna County
Solar
38.0 MWWithdrawn / abandoned Fluvanna, VAPJM May 2021target 2026
Solar project AG1-067, Barren County
Solar
38.0 MWWithdrawn / abandoned Barren, KYPJM Jul 2020target 2023
Solar project AF2-127, Defiance County
Solar
38.0 MWWithdrawn / abandoned Defiance, OHPJM Feb 2020target 2022
Solar project AH1-532, Marion County
Solar
37.8 MWWithdrawn / abandoned Marion, KYPJM Sep 2021target 2025
Solar + storage project AG2-605, Amherst County
Solar + storage
37.0 MWWithdrawn / abandoned Amherst, VAPJM Mar 2021target 2024
Gas project C09, Bergen County
Gas
37.0 MWWithdrawn / abandoned Bergen, NJPJM Feb 2000
Solar project AF2-220, Pulaski County
Solar
37.0 MWWithdrawn / abandoned Pulaski, VAPJM Mar 2020target 2023
Hydro project AG1-292, Beaver County
Hydro
36.6 MWWithdrawn / abandoned Beaver, PAPJM Sep 2020target 2023
Solar project AB2-090, Mecklenburg County
Solar
36.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Apr 2016target 2018
Gas project Z1-021, Defiance County
Gas
36.0 MWWithdrawn / abandoned Defiance, OHPJM Jun 2013target 2014
Gas project Z2-091, Butler County
Gas
36.0 MWWithdrawn / abandoned Butler, OHPJM Apr 2014target 2014
Page 51 of 105

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)